Close

LOGIN

Remember me
Not a member?
or
Connect using:
Why BS?

We encourage visitors to register on Business Standard. Registering on the site is absolutely Free and offers you the following benefits.

Free Daily E-newsletter

Breaking News Alerts in your Inbox

Post Comments and Share your Feedback

Your Personal Business Standard Page

Free Portfolio of Stocks, Equity and Commodities Derivatives

Access Premium Services

Receive Selective Offers from our Third Party Premium Advertisers

Get Invited to Business Standard Events

Close

FORGOT PASSWORD?

Not a member?

Fuel shortage hurting power generation: NTPC

Read more on:    NTPC | fuel shortage | power generation
Related News

Hit by , the country's largest power producer is generating as much as 10% less electricity, a top company official has said.

Noting that the fuel situation is very bad, NTPC Chairman and Managing Director Arup Roy Choudhury said it was hurting the company.

"We are running around every week... You can see, we are also most generating may be 7, 8 or 10% less than we could have because of fuel shortage," he told PTI.

State-owned NTPC has an installed generation capacity of 36,014 MW, with coal-fired plants alone accounting for 28,195 MW. Last fiscal, the company generated 220.54 billion units, accounting for more than 27% of total electricity generated in the country.

The Central Electricity Authority (CEA) data shows that as many as 37 thermal power stations had coal stocks for less than seven days as on March 20.

On the back of acute coal shortage impacting the power sector, the government recently has initiated various steps, including announcement from the Prime Minister's Office (PMO) last month that Coal India would ink FSAs before March-end, for power plants that have been commissioned up to December last year.

Meanwhile, Choudhury said the company is targeting a capital expenditure of Rs 20,900 crore for 2012-13. All the requisite funds have been tied up.

On possible capacity addition next fiscal, he said, "We are averaging about 3,000 MW. That is the optimistic figure."

For the 12th Five-Year Plan (2012-17), NTPC would be looking at a capital expenditure of Rs 2,15,000.

NTPC expects to have a total generation capacity of over 1,28,000 MW by 2032.

Read more on:   
|
|

Read More

Godrej Properties sells 49% stake in its arm to PE fund

Realty firm Godrej Properties Ltd today said it has sold 49% stake in its subsidiary, Godrej Landmark Redevelopers, to private equity firm ASK ...

Advertisements

Back to Top

Quick Links

Back to Top