You are here: Home » Companies » News
Business Standard

GAIL resumes cargo operations at Dabhol

Port resumes after the company repaired the fenders at the port that were damaged by rough sea

Press Trust of India  |  New Delhi 

State-owned gas utility India has resumed operations at the nation's third liquefied natural gas (LNG) terminal at after it repaired fenders at the port that were damaged by rough sea.

A ship carrying maiden or the so called commissioning cargo, which will be used to prepare the site for commercial operations, had to move to high seas after the fenders lining the jetty got damaged.

Fenders are bumpers used to absorb the kinetic energy of a berthing boat or vessel against the jetty.

Company officials said the fenders have been repaired and the ship has started discharging the

The carrier, called Excelerate, at the end of March brought a from Statoil ASA Snohvit plant in the Barents Sea off Norway.

It had offloaded barely 5-10% of the when operations had to be suspended last week and the vessel shifted to anchor.

"The vessel is back at the jetty and has begun to be discharged from today," an official said adding the commissioning of the terminal will take few weeks as systems are being tested one by one.

owns 31.52% stake in Ratnagiri Gas and Power Co Ltd -- the firm that owns the 1967 MW power plant and adjacent 5 million tons a year import terminal at in Maharashtra. The power plant and terminal were built by now bankrupt US energy major Enron Corp about a decade back.

Since it had been shut for so long, is taking all precautions in commissioning the terminal. The pipelines, storage tanks and other system are one-by-one tested by lowering temperature to minus 160 degrees Celsius.

is natural gas that has been liquefied at minus 160 degrees Celsius for ease of transportation in ships. Once received, is re-converted into its gaseous state and transported through pipelines to users like power plants.

Sources said the Belgian ship brought the commissioning of 138,000 cubic metres around March 25 and was to start offloading from March 28.

However, the offloading was delayed as the shallow navigation channel to the port kept the ship away from the jetty for almost three weeks.

Ratnagiri Gas and Power Co (RGPPL) took over in 2005 after the Enron's bankruptcy. The terminal was 70-80% complete when RGPPL took over the plant.

mechanically completed the plant in late 2010 and dredging work of the sea-channel leading to the port was completed last year.

First Published: Fri, April 27 2012. 14:46 IST
RECOMMENDED FOR YOU