Maldives wins airport dispute with GMR

Reuters  |  SINGAPORE/MALE  

The has won a court case allowing it to cancel a $511 million development with Infrastructure , clearing the way for it to take over its main airport.

The for Ibrahim Nasir International Airport, agreed in 2010, was the largest foreign investment in the south Asian tropical island chain famous for its luxury beach resorts popular with honeymooners and scuba divers.

But it has become embroiled in a bitter political argument, threatening to cloud foreign investor sentiment towards a country seeking overseas cash for many of its tourism projects.

"The government has the power to do what it wants, including expropriating the airport," Sundaresh Menon, the Chief Justice of Singapore, said in court on Thursday.

His ruling came after won a brief reprieve on Monday when a court order suspended the government's decision to cancel the contract, although the still pressed ahead with plans to take over the airport.

A spokesman for the president said the government would call for international tenders in about 18 months to continue with the modernisation.

Shares in Infrastructure were down as much as 4.2 percent following the ruling after earlier being in positive territory on the day. They later pared some of those losses.

Andrew Harrison, chief executive officer of the project, said it was too soon to discuss the practicalities of a handover.

"We've always been advocates of following the law. We are waiting to review the full judgment, which is currently being written up. It is too early to comment officially. We will have a staff briefing tomorrow afternoon," he told Reuters.

employs 1,800 people at the airport, 95 percent of whom are locals.

"We will take over. We will enroll all those people from who wish to join. Those who don't can go home. By Friday midnight we will take over," Imad Masood, the president's media spokesman, told Reuters, adding that the would pay compensation to GMR.

The two sides have not yet agreed on terms of compensation.

"We will go for international tenders maybe in one-and-half years from now. But they will be very transparent," he added.

The Maldives, south-west of India, terminated an agreement with last week, rattling its relations with its neighbour.

"is the biggest Indian investment in Male and we are only insisting for adherence to the legal process. Nothing more, nothing less," Syed Akbaruddhin, spokesman for India's foreign ministry, said on Thursday.

The cancellation of the follows a year of political turmoil in the that saw the ousting of its former president and months of unrest.

The to upgrade and operate the and build a new terminal came after a global tender overseen by the World Bank and signed under former president Mohamed Nasheed's administration.

The project was implemented through a joint venture company comprising Infrastructure Limited and Malaysia Airports Holding Berhad .

However, Nasheed's rivals filed legal action saying the was invalid as it contained a $25 development charge per outgoing passenger which was not authorised by parliament.

 

RECOMMENDED FOR YOU

Maldives wins airport dispute with GMR

The Maldives has won a court case allowing it to cancel a $511 million airport development contract with GMR Infrastructure , clearing the way for it to take over its main airport.

The has won a court case allowing it to cancel a $511 million development with Infrastructure , clearing the way for it to take over its main airport.

The for Ibrahim Nasir International Airport, agreed in 2010, was the largest foreign investment in the south Asian tropical island chain famous for its luxury beach resorts popular with honeymooners and scuba divers.

But it has become embroiled in a bitter political argument, threatening to cloud foreign investor sentiment towards a country seeking overseas cash for many of its tourism projects.

"The government has the power to do what it wants, including expropriating the airport," Sundaresh Menon, the Chief Justice of Singapore, said in court on Thursday.

His ruling came after won a brief reprieve on Monday when a court order suspended the government's decision to cancel the contract, although the still pressed ahead with plans to take over the airport.

A spokesman for the president said the government would call for international tenders in about 18 months to continue with the modernisation.

Shares in Infrastructure were down as much as 4.2 percent following the ruling after earlier being in positive territory on the day. They later pared some of those losses.

Andrew Harrison, chief executive officer of the project, said it was too soon to discuss the practicalities of a handover.

"We've always been advocates of following the law. We are waiting to review the full judgment, which is currently being written up. It is too early to comment officially. We will have a staff briefing tomorrow afternoon," he told Reuters.

employs 1,800 people at the airport, 95 percent of whom are locals.

"We will take over. We will enroll all those people from who wish to join. Those who don't can go home. By Friday midnight we will take over," Imad Masood, the president's media spokesman, told Reuters, adding that the would pay compensation to GMR.

The two sides have not yet agreed on terms of compensation.

"We will go for international tenders maybe in one-and-half years from now. But they will be very transparent," he added.

The Maldives, south-west of India, terminated an agreement with last week, rattling its relations with its neighbour.

"is the biggest Indian investment in Male and we are only insisting for adherence to the legal process. Nothing more, nothing less," Syed Akbaruddhin, spokesman for India's foreign ministry, said on Thursday.

The cancellation of the follows a year of political turmoil in the that saw the ousting of its former president and months of unrest.

The to upgrade and operate the and build a new terminal came after a global tender overseen by the World Bank and signed under former president Mohamed Nasheed's administration.

The project was implemented through a joint venture company comprising Infrastructure Limited and Malaysia Airports Holding Berhad .

However, Nasheed's rivals filed legal action saying the was invalid as it contained a $25 development charge per outgoing passenger which was not authorised by parliament.

 

image
Business Standard
177 22

Maldives wins airport dispute with GMR

The has won a court case allowing it to cancel a $511 million development with Infrastructure , clearing the way for it to take over its main airport.

The for Ibrahim Nasir International Airport, agreed in 2010, was the largest foreign investment in the south Asian tropical island chain famous for its luxury beach resorts popular with honeymooners and scuba divers.

But it has become embroiled in a bitter political argument, threatening to cloud foreign investor sentiment towards a country seeking overseas cash for many of its tourism projects.

"The government has the power to do what it wants, including expropriating the airport," Sundaresh Menon, the Chief Justice of Singapore, said in court on Thursday.

His ruling came after won a brief reprieve on Monday when a court order suspended the government's decision to cancel the contract, although the still pressed ahead with plans to take over the airport.

A spokesman for the president said the government would call for international tenders in about 18 months to continue with the modernisation.

Shares in Infrastructure were down as much as 4.2 percent following the ruling after earlier being in positive territory on the day. They later pared some of those losses.

Andrew Harrison, chief executive officer of the project, said it was too soon to discuss the practicalities of a handover.

"We've always been advocates of following the law. We are waiting to review the full judgment, which is currently being written up. It is too early to comment officially. We will have a staff briefing tomorrow afternoon," he told Reuters.

employs 1,800 people at the airport, 95 percent of whom are locals.

"We will take over. We will enroll all those people from who wish to join. Those who don't can go home. By Friday midnight we will take over," Imad Masood, the president's media spokesman, told Reuters, adding that the would pay compensation to GMR.

The two sides have not yet agreed on terms of compensation.

"We will go for international tenders maybe in one-and-half years from now. But they will be very transparent," he added.

The Maldives, south-west of India, terminated an agreement with last week, rattling its relations with its neighbour.

"is the biggest Indian investment in Male and we are only insisting for adherence to the legal process. Nothing more, nothing less," Syed Akbaruddhin, spokesman for India's foreign ministry, said on Thursday.

The cancellation of the follows a year of political turmoil in the that saw the ousting of its former president and months of unrest.

The to upgrade and operate the and build a new terminal came after a global tender overseen by the World Bank and signed under former president Mohamed Nasheed's administration.

The project was implemented through a joint venture company comprising Infrastructure Limited and Malaysia Airports Holding Berhad .

However, Nasheed's rivals filed legal action saying the was invalid as it contained a $25 development charge per outgoing passenger which was not authorised by parliament.

 

image
Business Standard
177 22

Upgrade To Premium Services

Welcome User

Business Standard is happy to inform you of the launch of "Business Standard Premium Services"

As a premium subscriber you get an across device unfettered access to a range of services which include:

  • Access Exclusive content - articles, features & opinion pieces
  • Weekly Industry/Genre specific newsletters - Choose multiple industries/genres
  • Access to 17 plus years of content archives
  • Set Stock price alerts for your portfolio and watch list and get them delivered to your e-mail box
  • End of day news alerts on 5 companies (via email)
  • NEW: Get seamless access to WSJ.com at a great price. No additional sign-up required.
 

Premium Services

In Partnership with

 

Dear Guest,

 

Welcome to the premium services of Business Standard brought to you courtesy FIS.
Kindly visit the Manage my subscription page to discover the benefits of this programme.

Enjoy Reading!
Team Business Standard