Business Standard

No radiation leak at Rajasthan nuclear unit

Sanjay Jog  |  Mumbai 

on Friday clarified there had not been any radioactive leakage into the environment from the Rajasthan Atomic Power Station (RAPS).

All nuclear reactors at the site are safe. There are six units, of which Unit I has been shut for long. At present, four reactors are operating and Unit V is under start-up after completion of a planned biennial shutdown.

N Nagaich, executive director, said an incident of tritium uptake had happened in Unit-IV when under planned biennial shutdown.

The Investigation Level of the tritium uptake is defined conservatively at about 1/10 th of the authorised annual limit specified by the regulatory body. There was absolutely no release of radiation into the environment. The workers are continuing to perform their normal duties, albeit in other areas of the station, Nagaich said.

According to Nagaich, all the persons involved in the work were monitored as a regular practice. Only two persons are likely to exceed the annual exposure limits specified by the regulatory body.

The exposure of other persons is below the annual exposure limit specified. They have been assigned the work in non- radioactive areas as per the prevailing procedure applicable in such cases.

The incident was immediately reported to Atomic Energy Regulatory Board (AERB). The incident has been investigated by the committee deputed by NPCIL and by independently. The appropriate measures as suggested by these committees to prevent such incidents in future, will be implemented promptly.

The incident occurred when a modification work, as planned during the shutdown, for assuring a provision of alternate water addition to the moderator system in the reactor -5 was being carried out. The uptake occurred due to inadvertent rise in tritium levels in a localized area of the containment building of the reactor -5. The localized increase in the Tritium concentration occurred due to the opening of the moderator cover gas line where the welding jobs were to be performed. Tritium, a heavier isotope is formed from heavy water during operation of the plant. Small quantities of Tritium exist in the form of vapour in the reactor building.

RECOMMENDED FOR YOU

No radiation leak at Rajasthan nuclear unit

Nuclear Power Corporation on Friday clarified there had not been any radioactive leakage into the environment from the Rajasthan Atomic Power Station (RAPS).

on Friday clarified there had not been any radioactive leakage into the environment from the Rajasthan Atomic Power Station (RAPS).

All nuclear reactors at the site are safe. There are six units, of which Unit I has been shut for long. At present, four reactors are operating and Unit V is under start-up after completion of a planned biennial shutdown.

N Nagaich, executive director, said an incident of tritium uptake had happened in Unit-IV when under planned biennial shutdown.

The Investigation Level of the tritium uptake is defined conservatively at about 1/10 th of the authorised annual limit specified by the regulatory body. There was absolutely no release of radiation into the environment. The workers are continuing to perform their normal duties, albeit in other areas of the station, Nagaich said.

According to Nagaich, all the persons involved in the work were monitored as a regular practice. Only two persons are likely to exceed the annual exposure limits specified by the regulatory body.

The exposure of other persons is below the annual exposure limit specified. They have been assigned the work in non- radioactive areas as per the prevailing procedure applicable in such cases.

The incident was immediately reported to Atomic Energy Regulatory Board (AERB). The incident has been investigated by the committee deputed by NPCIL and by independently. The appropriate measures as suggested by these committees to prevent such incidents in future, will be implemented promptly.

The incident occurred when a modification work, as planned during the shutdown, for assuring a provision of alternate water addition to the moderator system in the reactor -5 was being carried out. The uptake occurred due to inadvertent rise in tritium levels in a localized area of the containment building of the reactor -5. The localized increase in the Tritium concentration occurred due to the opening of the moderator cover gas line where the welding jobs were to be performed. Tritium, a heavier isotope is formed from heavy water during operation of the plant. Small quantities of Tritium exist in the form of vapour in the reactor building.

image
Business Standard
177 22

No radiation leak at Rajasthan nuclear unit

on Friday clarified there had not been any radioactive leakage into the environment from the Rajasthan Atomic Power Station (RAPS).

All nuclear reactors at the site are safe. There are six units, of which Unit I has been shut for long. At present, four reactors are operating and Unit V is under start-up after completion of a planned biennial shutdown.

N Nagaich, executive director, said an incident of tritium uptake had happened in Unit-IV when under planned biennial shutdown.

The Investigation Level of the tritium uptake is defined conservatively at about 1/10 th of the authorised annual limit specified by the regulatory body. There was absolutely no release of radiation into the environment. The workers are continuing to perform their normal duties, albeit in other areas of the station, Nagaich said.

According to Nagaich, all the persons involved in the work were monitored as a regular practice. Only two persons are likely to exceed the annual exposure limits specified by the regulatory body.

The exposure of other persons is below the annual exposure limit specified. They have been assigned the work in non- radioactive areas as per the prevailing procedure applicable in such cases.

The incident was immediately reported to Atomic Energy Regulatory Board (AERB). The incident has been investigated by the committee deputed by NPCIL and by independently. The appropriate measures as suggested by these committees to prevent such incidents in future, will be implemented promptly.

The incident occurred when a modification work, as planned during the shutdown, for assuring a provision of alternate water addition to the moderator system in the reactor -5 was being carried out. The uptake occurred due to inadvertent rise in tritium levels in a localized area of the containment building of the reactor -5. The localized increase in the Tritium concentration occurred due to the opening of the moderator cover gas line where the welding jobs were to be performed. Tritium, a heavier isotope is formed from heavy water during operation of the plant. Small quantities of Tritium exist in the form of vapour in the reactor building.

image
Business Standard
177 22

Upgrade To Premium Services

Welcome User

Business Standard is happy to inform you of the launch of "Business Standard Premium Services"

As a premium subscriber you get an across device unfettered access to a range of services which include:

  • Access Exclusive content - articles, features & opinion pieces
  • Weekly Industry/Genre specific newsletters - Choose multiple industries/genres
  • Access to 17 plus years of content archives
  • Set Stock price alerts for your portfolio and watch list and get them delivered to your e-mail box
  • End of day news alerts on 5 companies (via email)
  • NEW: Get seamless access to WSJ.com at a great price. No additional sign-up required.
 

Premium Services

In Partnership with

 

Dear Guest,

 

Welcome to the premium services of Business Standard brought to you courtesy FIS.
Kindly visit the Manage my subscription page to discover the benefits of this programme.

Enjoy Reading!
Team Business Standard