State-owned power equipment maker said today that it has secured an order worth Rs 215 crore for renovation and modernisation of electrostatic precipitators (ESPs) at Kahalgaon Super Thermal Power Station (STPS) in Bihar.

Originally supplied along with the four units (4X210 MW) by Bhel, the ESPs have been in operation for more than 25 years since their commissioning, the company said in a statement.


Renovation of these ESPs will enable these units to meet the new norms for suspended particulate matter (SPM) emission, recently announced by the Ministry of Environment, Forest and Climate Change (MOEF & CC). Modernisation of the units will facilitate the operation of these units for many more years.

Bhels scope of work in the contract includes design, engineering, manufacture, supply and commissioning of the ESPs to bring down the SPM emission to the stipulated level for all the four units of Kahalgaon STPS, Stage-1.

Major equipment for the project will be supplied by Bhels units located at Ranipet and Bhopal, while the execution on site will be undertaken by Power Sector Eastern Region.

(This story has not been edited by Business Standard staff and is auto-generated from a syndicated feed.)

First Published: Tue, December 05 2017. 14:15 IST