A bridge too far
Bandra-Worli Sea Link a poor example of urban planning
Business Standard /  June 30, 2009, 8:53 IST

The Mumbai commuter’s travel time between the Bandra flyover and Love Grove Junction at Worli is set to come down from 35 minutes to seven minutes from today, with the inauguration of the 5.6 km Sea Link, including India’s first cable-stayed bridge in the open sea. Yes, but only if wishes are horses. The sevenminute timeframe for the 7.7 km distance between the two points was promised by the Maharashtra government; like most government promises, this one will remain a pipedream. The reason is that the speed limit on the sea link has already been reduced from the original 80 kmph to 50 kmph. While even that would be a vast improvement on the peak-hour crawl on the existing land route, the problem begins at the point where the Sea Link meets the Worli Sea Face at (believe it or not) a 90-degree angle. The one-km stretch towards Love Grove Junction that then connects to the south and central business districts has a speed limit of 30 kmph, five traffic signals, and an equal number of diversions and curves. That last stretch alone could take 10-15 minutes, and cause traffic to back up onto the sea link. And, a motorist would have to pay Rs 50 (the one-way toll) to save perhaps 15 minutes of travel time.

 
 
Related Stories
News Now
-Bandra-Worli sea link opens today
-Bandra-Worli sea link to consume 1,000 Kw power a day
-Bandra-Worli sea links weighs equals to 50k African elephants
-Reliance Infrastructure looking at domestic banks to push projects

 

There are no answers on why no city planner could work out channels for efficient traffic dispersal. There were plans to build a flyover in Worli to take on the traffic spilling from the bridge. There were also plans to build a 4.3 km flyover at Peddar Road in South Mumbai to carry the traffic from the sea link. None of these projects has seen the light of day as the state government has failed to obtain environment clearances. There has also been talk of a skywalk to solve the problems of pedestrians, but that too hangs fire.

 

It is amazing how the bridge, which adds such an impressive dimension to Mumbai’s skyline and held so much promise for easing the traffic woes of the city’s western suburbs, can be a victim of such poor planning. It is not that time was short for a proper traffic dispersal plan. The bridge has taken eight years to build, four more than scheduled, because of design changes, environment clearance delays and a slew of law suits. And this is just the first of the three-phase Western Freeway project. Work on the other two phases, linking Worli to Haji Ali and Haji Ali to Nariman Point, hasn’t started yet. While the second phase will take another four years to build, the Maharashtra State Road Transport Corporation is still awaiting cabinet approval for its revised proposal for the third phase. By way of comparison, China’s 36 km Hangzhou Bay Bridge, the world’s longest sea-crossing bridge, over seven times the length of the Mumbai bridge, took all of four years. Also, that country has built seven sea links in the past six years.

 

 

Arrow Other Stories     
- Sensex makes remarkable recovery, regains 17K
- Koda says he will report to ED only after Jharkhand polls
- Nepal's dethroned king Gyanendra gets first passport
- Two Pakistanis linked to Mumbai attacks arrested in Italy
- India attaches high priority to ties with US: PM
More  
  Read Business news in 
  Get financial advisory and solutions for your projects
  Holidays starting at a delightful EMI of Rs 3481
  Switch on and say hello to Monday morning !
  Your dream home can now be a reality.
  Visit Fortis for a preventive health check-up & get a 20% discount.
  Follow the ups and downs of your investments. Try our new Portfolio Tracker
  Kolkata Dock \ Freight contract for the British Gurkhas Nepal
  Find how Midsize Businesses use ERP to gain competitive advantage
  Trading in Forex is now as easy as 1-2-3
  Discover an economical and cost effective way to market your products and services
  Giftwithlove.com: Same day delivery of Flowers and Cakes to India
  Download the E-book on the Future of Business Intelligence
  Learn Best Practices for improving customer satisfaction
  Know your customers better... download the free e-book on CRM
   Discussion Board / User Comments    
Display Name  Email-Id  
Post your comment
Phil
This does seem to be just another (fancy) road, built where it was possible to do so, though at tremendous cost. One question which crops up is: is it possible to decouple the environmental and legal clearances from the actual construction? The latter should be non-stop (subject to day-to- day environmental factors, such as tidal movements etc). Once the former are done then the design should be frozen for construction purposes. The pre-construction and construction phases should be put under the scanner at the earliest to pinpoint the sources of delays etc. The post-mortem should then be used urgently for the benefit of other projects in the pipeline.
Reply
Vijay
The caption should have been aptly named "A Bridge to Nowhere !"
Reply
Most Popular
Read
E-Mailed
Commented
   
- Bharti Airtel slashes roaming rates by 60%
- Govt may allow private sector investment in education
- Network18 lays off 200 staffers
- Suzlon Energy's three promoters pledge 2.8 cr shares
- Patni may host all IT services on 'cloud'
 
 More  
BS Poll
Cast Your Vote
 
   
 
Should India's defence sector be thrown open to foreign investments?
  Yes  No
Submit

  Hot Searches  
 
Amitabh Bachchan | N Chandrasekaran | Swine Flu | Mukesh Ambani | Anil Ambani | TCS | Infosys |  Air India |  Duronto |  Pranab Mukherjee | Sonia Gandhi | Congress | Rahul Gandhi |  Bigg Boss |  New Pension Scheme |  Service tax |  Excise duty |  Sebi | Tech Mahindra |  Ramalinga Raju |  Satyam |  Reliance  |  RBI |  GDP |  Gold |  Ratan Tata |  ICICI |  |  B-School | DLF  Sensex |  Tax calculator | Home Loan  | Bollywood | Personal Finance |  inflation | oil prices |  World Bank | Reliance Infratel |  HDFC |  Barack Obama  
  Member Area Write to the Editor RSS Archives Advanced Search
  Subscribe to BS print product BS e-paper Newsletter Portfolio Tracker
  BS Products BS Hindi BS Motoring
FOR HOT PRODUCTS
BS Bazaar.com
Home | Markets & Investing | Companies & Industry | Banking & Finance | Economy & Policy | Opinion
Life & Leisure | Management & Marketing | Tech World
About Us | Partner With Us | Code of Conduct | Careers | Advertise with us| Terms & Conditions | Disclaimer | Site Map | Contact Us | Feedback