Midsize developers deploy ERP to curb project delays
Archana M Prasanna / Chennai/ Bangalore Dec 31, 2009, 00:48 IST

Pilots of ERP on in prestigious projects

With delays plaguing many a real estate project, small and mid-sized developers are starting to look at web-based solutions to help them work closer to their deadlines. The move is being seen as an effort to curb cost over-runs.

A case in point is the Bangalore-based SNC Power Corp which specialises in power projects. The company is presently working on a 500 Mw power project in Bellary in Karnataka and a 250 Mw plant in Chandrapura in Jharkhand. It set up a pilot project for an ERP solution for a gas-based power project in Tripura for the ONGC, and based on the results is evaluating deploying it at its other projects as well.

Vybhav Shetty, executive director, SNC Power Corp said the need to shift to ERP comes at a time when delays are prevalent in the industry. “Delays could come about because of several factors in the industry like clients, internal problems, local agitation, material shortage or other delays. We have also been affected by delays in a couple of projects, by at least 15 per cent,” he said.

“We have undertaken an ERP pilot to streamline our processes, collect data from site, remotely fed to the system and process it so that management has access to information. Our cost centres are spread to different regions. We needed to integrate all systems and process the data to facilitate management to take appropriate action,” he said.

Similarly, RDS projects, which is involved in IT and infrastructure projects has also deployed an ERP management solution as a pilot test for a Rs 42 crore aviation project. “There is a greater need for visibility at the central level. Without this, it would be difficult to complete projects on time. We are looking to adapt to an ERP solution in a phased manner for our projects,” he said. The company has an order book of around Rs 500 crore. He added that with prices having come down owing to the financial meltdown, it was essential for companies to keep a tab on the project status and cost control to improve their margins.

It is not surprising that companies are eager to deploy web-based management solutions. On an average, cost over-runs in projects stand around 10-15 per cent and time delays range from three months to 12 months which have negative repurcussions on business, say industry players..

According to a study by real estate research firm PropEquity, most cities in the country have been plagued with delay issues since 2008. The study found that Bangalore witnessed the highest number of delays among projects scheduled for completion in 2008 where 309 of the 575 projects were delayed and the average delay in these projects was nine months. In places like Ghaziabad and Gurgaon, 71 per cent of projects were delayed, as against the total number of projects scheduled for completion in 2008 and onwards.

“A lot of developers were diverting funds meant for a project to other projects. Hence cash flows are an issue. Their order book was more than what they could actually execute. Many smaller developers jumped into the property sector and they could not complete the projects, resulting in delays,” Samir Jasuja, founder and chief executive, PropEquity said in the study.

Industry experts say that in the race to make competitive bids for projects, companies rarely focus on their implementation process which eventually bogs them down. Balaji Sreenivasan, CEO of Aurigo SoftwareTechnologies, which provides web-based solutions for capital project, facilities, real estate and construction management said that in a globally competitive industry, every move of the company is closely watched and a history of project delays would not bode well for them.

“With effective project management systems in place, a company can expect a 5-7 per cent reduction in cost overruns and curb time delays by a few months,” said Sreenivasan.

It is not just corporate houses shifting to technology, even public enterprises like the Railways are keen on adopting project management systems. The Southern Railway is looking to automate its processes and has deployed a pilot solution in its project to double the railway line from Sengalpet to Villupuram. It is also looking to use the solution for its MRTS project from Velachery to St Thomas Mount in Chennai.

“We spend around Rs 1,200 crore each year in infrastructure projects in the southern region. We want to get into a new type of thinking for speeding up our projects resulting in better management,” said Ramanathan, chief administrative officer, Southern Railway.

With a price tag of anything between Rs 50 lakh to over Rs 2 crore, the cost has so far been a deterrent to small and mid-size companies. However, more and more companies are exploring the option in select projects. “When faced with the alternative of wastage of money and resources due to improper allocation, companies are preferring to invest in a dependable management solution, added Sreenivasan.

New Ipad Application :Business Standard's all new IPad App
Click here to download for free
Arrow Other Stories     
- Markets end lower ahead of May F&O expiry
- Parsvnath posts Rs 23 cr loss in Q4
- Educomp net down 57% at Rs 61 cr in Jan-Mar qtr
- DLF Q4 net plunges 39% to Rs 211 cr
- Provogue Q4 net profit down 71% at Rs 1.81 cr
  Read Business news in 
- India's no. 1 Property Site. Click here to know more
- 
- "Discover The Power of One"
- Help a Child Achieve her. Click to know more
- The Best Seller is Also the No. 1 in Mileage. Click here
- Watch The Film Here. Click here to know more..
- Learn How One City is Running on FOOD SCRAPS.
- 1 billion in saving for Unilever without any tangles.
- A Brand New Server at a Price That Fits Your Budget. Click here
- One Partnership Endless Possibilities. Click here to know more
- Helping doctors detect diseases earlier, saving costs & extending lives.
- Which is the best plan for your daughter
- Check out the TRUE COLOURS of your Stocks, Now for FREE!
- One of the leading business schools in the world.Know More
- 2 Lac Apartments, 1 Lac House / Plots. Click here
Sorry, comments to this story are closed
Latest Messages
Table for Two
  Now available at Special price
  Rs.280/- Only

  Buy Now
BS POLL
UPA 2 has completed three years. How do you rate its performance?  Read the story
  Good
  Average
  Bad
Submit
Most Popular
Read
E-Mailed
Commented
   
- Vodafone notice on arbitration premature: Govt
- Coal blocks for infrastructure projects get GoM nod
- Dissidence brewing in state: Senior BJP leaders team up against Modi
- Rupee-sensitive stocks risky for new investors
- Tata Motors skids as margins dip at JLR
 
 More  
Tax Shastra
  Now available at Special price
  Rs. 360/- Only

  Buy Now
 
  Member Area Write to the Editor RSS Archives Advanced Search
  Subscribe to BS print product BS e-paper Newsletter Portfolio Tracker
  BS Products BS Hindi BS Motoring BS Books
Home | Markets & Investing | Companies & Industry | Banking & Finance | Economy & Policy | Opinion
Life & Leisure | Management & Marketing | Tech World | General News
About Us | Partner With Us | Code of Conduct | Careers | Advertise with us| Terms & Conditions | Disclaimer | Contact Us