New highway bidding scheme to save time
Mihir Mishra / New Delhi Sep 21, 2009, 00:15 IST

Pre-selection likely to save 18 months.

Under a new policy, all road highway projects are to be earmarked from the beginning to one of three processes of bidding, on the basis of its financial viability. This pre-selection is estimated to save up to 18 months of time.

Earlier, every project was first put under the build operate and transfer (BOT) toll bidding process. If there was no positive response, it was put under the BOT annuity bidding process, where the contractor is paid every six months and the toll is collected by the government. A third option was an engineering procurement and construction (EPC) contract.

However, the process of trying different bidding processes would take about six months at every phase, and so, an escalation in project cost. And, the government failed to meet the target date of completion.

Under the new plan, all projects are divided into three categories — BOT-toll, BOT-annuity or EPC — even before the bidding process starts. “Preparing the project up for bid on a new scheme consumes six months every time. And if it is pre-decided, we will save those 18 months,” said a senior official of the National Highways Authority of India (NHAI).

“This scheme will obviously save a lot of time, but a time limit should also be set for projects on annuity and EPC. The concessionaires make sure that the projects on BOT (toll) are completed in time, but the same is not the case with projects on annuity and EPC,” said M Murali, director-general, National Highways Builders Federation.

NHAI is aiming at putting 126 projects out for bids, worth Rs 1 lakh crore, this financial year. It has, under the new policy, identified 6,831 km to be bid on toll, 1,143 km on annuity and 3,954 km on EPC.

The road transport and highways ministry also proposes to build a huge network of expressways by 2022, also the final year of the Thirteenth Five-Year Plan. The ministry plans to build expressways in three phases — by 2012, 2017 and 2022 — and, accordingly, it has prepared a draft report for a network of the proposed 17,661 km of stretches.

The World Bank has agreed to provide a $3-billion loan for developing national highways. The assistance will be utilised for converting 6,372 km of one-lane highways into two lanes, of the 19,702-km of single-lane highways. The total project cost for 2009-10 has been estimated at $20 billion.

New Ipad Application :Business Standard's all new IPad App
Click here to download for free
Arrow Other Stories     
- Markets end lower ahead of May F&O expiry
- Parsvnath posts Rs 23 cr loss in Q4
- Educomp net down 57% at Rs 61 cr in Jan-Mar qtr
- DLF Q4 net plunges 39% to Rs 211 cr
- Provogue Q4 net profit down 71% at Rs 1.81 cr
  Read Business news in 
- India's no. 1 Property Site. Click here to know more
- Help a Child Achieve her. Click to know more
- The Best Seller is Also the No. 1 in Mileage. Click here
- Watch The Film Here. Click here to know more..
- Learn How One City is Running on FOOD SCRAPS.
- 1 billion in saving for Unilever without any tangles.
- One Partnership Endless Possibilities. Click here to know more
- Helping doctors detect diseases earlier, saving costs & extending lives.
- Which is the best plan for your daughter
- Check out the TRUE COLOURS of your Stocks, Now for FREE!
- One of the leading business schools in the world.Know More
- 2 Lac Apartments, 1 Lac House / Plots. Click here
Sorry, comments to this story are closed
Latest Messages
Table for Two
  Now available at Special price
  Rs.280/- Only

  Buy Now
BS POLL
UPA 2 has completed three years. How do you rate its performance?  Read the story
  Good
  Average
  Bad
Submit
Most Popular
Read
E-Mailed
Commented
   
- Vodafone notice on arbitration premature: Govt
- Coal blocks for infrastructure projects get GoM nod
- Dissidence brewing in state: Senior BJP leaders team up against Modi
- Tata Motors skids as margins dip at JLR
- Rupee-sensitive stocks risky for new investors
 
 More  
New Ipad Application
 Business Standard's all new IPad  App
 Click here to download for free
  Hot Searches  
 
Apalya |  Air India |  GAAR |  Agni  |  Solar eclipse |  Satyamev Jayate |  SRK |  Aamir Khan |  IPL |  Ertiga |  Sarfaesi Act |  Vodafone |  JP Morgan |  Transfer pricing |  Rupee |  Kingfisher Airlines |  Silver |  Provident Fund |  income tax refund |  iPhone |  Reliance Industries |  SEBI |  BSNL |  BSE |  NSE |  Mukesh Ambani |  Anil Ambani |  Infosys |  Pranab Mukherjee |  Sonia Gandhi |  Rahul Gandhi |  New Pension Scheme |  Reliance |  RBI |  GDP |  Gold |  Ratan Tata |  ICICI |  B-School |  Sensex |  Tax calculator |  Home Loan |  Personal Finance |  inflation |  oil prices |  Barack Obama |   
 
  Member Area Write to the Editor RSS Archives Advanced Search
  Subscribe to BS print product BS e-paper Newsletter Portfolio Tracker
  BS Products BS Hindi BS Motoring BS Books
Home | Markets & Investing | Companies & Industry | Banking & Finance | Economy & Policy | Opinion
Life & Leisure | Management & Marketing | Tech World | General News
About Us | Partner With Us | Code of Conduct | Careers | Advertise with us| Terms & Conditions | Disclaimer | Contact Us