Slow pace of hydropower projects set to hit govt plans
Sudheer Pal Singh / New Delhi Apr 17, 2009, 00:58 IST

That the power capacity addition in the Eleventh Plan (2007-2012) is going to be below the targeted 78,700 Mw is fairly well-known. It is now evident that there will be a slippage in the capacity addition in the Twelfth Plan (2012-17) also due to the delays in hydropower projects.

The government had initially set a target of adding 30,000 Mw of hydropower capacity in the Twelfth Plan period but later lowered the target as only 25,000 Mw capacity was found to be feasible for the Plan.

 
There will be a slippage by at least a fifth of the target due to delays in submission of Detailed Project Reports (DPRs).

A DPR is a document in which the project developer mentions the technical and financial details of the project.

“DPRs for around 5,000 Mw are still under preparation. It is not possible that these projects can come up in the Twelfth Plan,” said a senior official from the Central Electricity Authority (CEA), the apex power sector planning body.

The development of a typical large-sized hydropower project — right from its conceptualisation to commissioning — requires at least 10 years in India. This includes, in the first stage, preparation of a preliminary feasibility report (PFR) by the developer based on a two-year long survey of the plant site.

This is followed by submission of DPRs to the CEA which accords necessary technical and financial approvals, after which the DPR is sent to the Ministry of Environment and Forest (MoEF) for environment clearances, which requires another 2-2.5 years. Finally, the last stage of actual construction of the project takes another five years for completion.

“The process, from evaluation of DPRs to construction, takes at least eight years. Even if the remaining DPRs are submitted today, the projects are unlikely to be completed by the end of the (Twelfth) Plan,” the official added.

Earlier this year, another senior official from the CEA, while explaining the reasons for the dismal growth in the hydropower sector in the country, had pointed out how the delays in preparation of DPRs were set to hit the government’s plans of adding even 25,000 Mw hydropower capacity in the next Plan.

“When we made the plan for the Twelfth Plan in September last year, we thought that the DPRs for this 25,000 Mw would be made available to the government by March 2009. But, as against the expected reports of 8,000 Mw, we could get reports for only 2,400 Mw,” he said. “5,600 Mw have already slipped from the target of completion by March 2009,” he added.

Asked why the DPRs were being delayed, the official said that most of the private power developers “do not have the requisite technical expertise and thus try to cut short on geological investigations. And in case minimum qualifications are not met, we do not accept the report for further examination”. Another area of constraint, according to the official, is that while the developers are many, consulting agencies are limited.
 

HYDROPOWER CAPACITY IN INDIA
  Installed hydel
capacity
(Mw)
Overall installed
capacity (Mw)
Percentage
11th Plan (Till Feb '09) 36,877 1,47,715 24
10th Plan 34,653 1,32,329 26
9th Plan 26,268 1,05,045 25

All this is set to adversely affect the hydro-thermal mix of power in the country. While hydropower capacity at the end of the Tenth Plan accounted for around 26.2 per cent of the overall installed capacity, it is projected to come down to 23.8 per cent at the end of the current Plan period and further down to 22.6 per cent at the end of the Twelfth Plan.

Industry experts believe that the private developers’ hesitation in submitting DPRs for such long-gestation projects is partly due to the current economic downturn.

“The current market situation has increased the time and cost overruns associated with the hydropower projects, which already require a higher equity participation from the developer as compared to thermal projects,” said Kuljit Singh, Head, Transaction Advisory Services, Ernst & Young. “Moreover, the developers have started realising that money may start coming back in hydropower projects only in 5-6 years, as compared to 3-4 years for thermal projects,” he added.

Singh also added that a lot of private developers had taken up hydropower projects to create a capacity bank and sell it later, “but the current market situation has made it difficult. Thus they are inclined towards delaying the projects”.

New Ipad Application :Business Standard's all new IPad App
Click here to download for free
Arrow Other Stories     
- Markets post worst May performace since 2006
- Kavveri Telecom Q4 net declines over 6%
- Wall Street opens flat on economy worries
- RIM to set up first BlackBerry innovation zone in India
- Rajaratnam bragged about sources of inside info: Gupta lawyers
  Read Business news in 
- India's no. 1 Property Site. Click here to know more
- Help a Child Achieve her. Click to know more
- Benefits Upto Rs. 2.36 Lakhs on the Fully Loaded TJet Petrol.
- The Best Seller is Also the No. 1 in Mileage. Click here
- Watch The Film Here. Click here to know more..
- Learn How One City is Running on FOOD SCRAPS.
- 1 billion in saving for Unilever without any tangles.
- One Partnership Endless Possibilities. Click here to know more
- Helping doctors detect diseases earlier, saving costs & extending lives.
- Which is the best plan for your daughter
- Check out the TRUE COLOURS of your Stocks, Now for FREE!
- One of the leading business schools in the world.Know More
- 2 Lac Apartments, 1 Lac House / Plots. Click here
Sorry, comments to this story are closed
Latest Messages
Table for Two
  Now available at Special price
  Rs.280/- Only

  Buy Now
BS POLL
UPA 2 has completed three years. How do you rate its performance?  Read the story
  Good
  Average
  Bad
Submit
Most Popular
Read
E-Mailed
Commented
   
- NDA-led bandh turns violent in Bangalore
- Investors wary as Flipkart shows growth pangs
- Army chief slams BEML on Tatra, awards it Rs 1,500-cr deal
- India announces austerity measures, cuts non-plan spend
- Kingfisher Airlines Q4 loss more than trebles
 
 More  
New Ipad Application
 Business Standard's all new IPad  App
 Click here to download for free
  Hot Searches  
 
Apalya |  Air India |  GAAR |  Agni  |  Solar eclipse |  Satyamev Jayate |  SRK |  Aamir Khan |  IPL |  Ertiga |  Sarfaesi Act |  Vodafone |  JP Morgan |  Transfer pricing |  Rupee |  Kingfisher Airlines |  Silver |  Provident Fund |  income tax refund |  iPhone |  Reliance Industries |  SEBI |  BSNL |  BSE |  NSE |  Mukesh Ambani |  Anil Ambani |  Infosys |  Pranab Mukherjee |  Sonia Gandhi |  Rahul Gandhi |  New Pension Scheme |  Reliance |  RBI |  GDP |  Gold |  Ratan Tata |  ICICI |  B-School |  Sensex |  Tax calculator |  Home Loan |  Personal Finance |  inflation |  oil prices |  Barack Obama |   
 
  Member Area Write to the Editor RSS Archives Advanced Search
  Subscribe to BS print product BS e-paper Newsletter Portfolio Tracker
  BS Products BS Hindi BS Motoring BS Books
Home | Markets & Investing | Companies & Industry | Banking & Finance | Economy & Policy | Opinion
Life & Leisure | Management & Marketing | Tech World | General News
About Us | Partner With Us | Code of Conduct | Careers | Advertise with us| Terms & Conditions | Disclaimer | Contact Us