Higher bank guarantee worry for R-Power's Tilaiya project

The company said in its tariff petition filed before CERC that land acquisition problems were delaying Rs 24,000-cr project

Katya B Naidu Mumbai
Last Updated : Oct 04 2013 | 3:07 AM IST
Reliance Power’s (R-Power) entire portfolio of ultra mega power projects (UMPPs) is in a trouble. Earlier this week, the company sought a tariff increase for the 4,000-Mw power plant at Tilaiya in Jharkhand, which is yet to get off the ground. The company said in its tariff petition filed before the Central Electricity Regulatory Commission (CERC) that land acquisition problems were delaying Rs 24,000-crore project.

R-Power had been facing various issues, including law and order problems, for starting work on the project. “Many employees have been worried and the company is finding it tough to recruit people for the project after one of its general managers were shot dead in Jharkhand while trying to acquire land,” said a company official.

Tilaiya is the toughest UMPP in its kitty, as its performance guarantees are twice as much as its other UMPPs, accounting to around Rs 600 crore. Five years back, when R-Power won the bid for its third UMPP at Tilaiya, it was made to pay twice as much in performance guarantee to the government.

The group had already won two UMPPs in the two years prior to bidding for Tilaiya, and the government felt it needed much more assurance to ensure that the then newly split company had the wherewithal to complete the 4,000-Mw project.

The company, which won the bid with Rs 1.77 a unit levelised tariff, had paid higher amount as performance guarantee. It paid Rs 240 crore as the bid bond, and Rs 600 crore was accounted in the form of bank guarantees. “This will make it very tough for the company to return the project,” said a government official. An email sent to the company did not elicit any response.

The company filed three petitions with CERC seeking relief for its Sasan UMPP in Madhya Pradesh due to rupee depreciation, change in law during the construction period, and change in law impacting revenue and costs during the operation period. The matter is still being examined by the CERC.

Both Tilaiya and Sasan have captive coal mines, which will provide fuel to the projects. Yet another power project, at Krishnapatnam in Andhra Pradesh, which is an imported coal-based power project, is also facing stalemate. Imported coal from Indonesia has become costlier for power generators after the country changed laws, forcing many power generators to seek permissions from the government to allow them to pass on increased fuel costs to the power purchasers. The company stalled work on Krishnapatnam as well, while Sasan has already commissioned one unit and others are under construction.

Only 19.5 per cent of the land required for the Tilaiya power plant, or 450 acres, has been acquired until now, according to the latest report on the project by the Central Electricity Authority. It is yet to acquire any land for the captive coal block.

While environment and forest clearances for Tilaiya power plant have been received, those for the coal blocks, ie Kerandari B & C blocks, are yet to come. The company has submitted a proposal for forest clearance to the state forest department.

R-Power has an operating power plant of 1,200 Mw at Rosa, Uttar Pradesh. This has been the only power project that it had finished after it raised Rs 11,560 crore through an initial public offering in early 2008.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Oct 04 2013 | 12:48 AM IST

Next Story