State-wise status of RERA: Most of them miss deadline, says report
Full text of CRISIL Research Impact Note on status of RERA
)
Explore Business Standard
Full text of CRISIL Research Impact Note on status of RERA
)
| States | Definition of on-going projects | Penalties for noncompliance | Payment schedule | Norms for escrow withdrawal | Clause for structural defects |
|---|---|---|---|---|---|
| Andhra Pradesh | Diluted | Diluted | In line | In line | In line |
| Bihar | In line | Diluted | Lacks clarity | In line | In line |
| Gujarat | Lacks clarity | Lacks clarity | Lacks clarity | Lacks clarity | Lacks clarity |
| Kerala | Diluted | In line | In line | Diluted | Diluted |
| Madhya Pradesh | In line | Diluted | Lacks clarity | Lacks clarity | Lacks clarity |
| Maharashtra | In line | Diluted | With conditions | In line | In line |
| Odisha | In line | Diluted | Lacks clarity | In line | In line |
| Rajasthan | In line | Diluted | In line | In line | Lacks clarity |
| Uttar Pradesh | Diluted | Diluted | Lacks clarity | In line | Lacks clarity |
| Andaman and Nicobar Islands | In line | In line | In line | In line | In line |
| Chandigarh | In line | In line | In line | In line | In line |
| Dadra and Nagar Haveli | In line | In line | In line | In line | In line |
| Daman and Diu | In line | In line | In line | In line | In line |
| Lakshadweep | In line | In line | In line | In line | In line |
| National Capital Territory of Delhi | In line | In line | In line | In line | In line |
| State | RERA notified on | CRISIL Research's comments |
|---|---|---|
| Andhra Pradesh | 27-Mar-17 | * Definition of ongoing projects: Diluted |
| Includes ongoing projects with conditions: excludes projects where roads, open spaces, amenities and services have been handed over to the local authority in layout projects, or where all slabs are laid in housing projects, or where all developmental works have been completed and sale/lease deeds of 50% of the apartments/houses/plots have been executed, or where development works have been completed and application has been filed to the competent authority for issue of completion or occupancy certificate. | ||
| *Penalties for non-compliance: Diluted | ||
| Compounding of offence clause included to avoid imprisonment; 10% of project cost as penalty. | ||
| *Payment schedule: In line | ||
| 10% advance payment, or an application fee from buyers while entering into a written agreement for sale. | ||
| *Norms for escrow withdrawal: In line | ||
| 70% of the amount realised by developers to be deposited in a separate account; withdrawal in proportion to the percentage of project completed. | ||
| *Clause for structural defects: In line | ||
| Time frame – defects arising within five years from possession; developers to rectify such defects without further charge within thirty days. | ||
| Bihar | 27-Apr-17 | * Definition of ongoing projects: In line |
| Includes projects that are ongoing on the date of commencement of the Act, and for which the completion certificate has not been issued. | ||
| *Penalties for non-compliance: Diluted | ||
| Compounding of offence clause included to avoid imprisonment; 10% of project cost as penalty. | ||
| *Payment schedule: Lacks clarity in the notified rules | ||
| *Norms for escrow withdrawal: In line | ||
| 70% of the amount realised by developers to be deposited in a separate account; withdrawal in proportion to the percentage of project completed. | ||
| *Clause for structural defects: In line | ||
| Time frame -within five years from possession; developers to rectify such defects without further charge within thirty days. | ||
| Gujarat | 29-Oct-16 | * Definition of on-going projects: Not mentioned in the notified rules |
| *Penalties for non-compliance: Not mentioned in the notified rules | ||
| *Payment schedule: Not mentioned in the notified rules | ||
| *Norms for escrow withdrawal: Not mentioned in the notified rules | ||
| *Clause for structural defects: Not mentioned in the notified rules | ||
| Kerala | 3-Feb-16 | * Definition of ongoing projects: Diluted |
| Includes ongoing projects with conditions: Excludes all on-going projects where the promoter has received all requisite approvals/permits for the development of the real estate project prior to commencement of the Act. | ||
| *Penalties for non-compliance: In line | ||
| Imprisonment for a term which may extend up to three years, or with fine which may extend up to 10% of the estimated cost of the real estate project, or both. | ||
| *Payment schedule: In line | ||
| 10% advance payment, or an application fee from buyers while entering into a written agreement for sale. | ||
| *Norms for escrow withdrawal: Diluted | ||
| 70% (or less, as notified by the government) of the amount realised by developers to be deposited in a separate account; no clarity on withdrawal mechanism. | ||
| *Clause for structural defects: Diluted | ||
| Time frame - Within five years from possession; developers to rectify such defects without further charge within thirty days. | ||
| Madhya Pradesh | 22-Oct-16 | * Definition of ongoing projects: In line |
| Includes projects that are ongoing on the date of commencement of the Act, and for which the completion certificate has not been issued. | ||
| *Penalties for non-compliance: Diluted | ||
| Compounding of offence clause included to avoid imprisonment; 10% of project cost as penalty. | ||
| *Payment schedule: Not mentioned in the notified rules | ||
| *Norms for escrow withdrawal: No clarity in the notified rules | ||
| *Clause for structural defects: Not mentioned in the notified rules | ||
| Maharashtra | 20-Apr-17 | * Definition of on-going projects: In line |
| Includes projects that are ongoing on the date of commencement of the Act, and for which completion certificate has not been issued. | ||
| *Penalties for non-compliance: Diluted | ||
| Does not mention imprisonment penalties; no clarity on monetary fines/penalties as percentage of total project cost. | ||
| *Payment schedule: In line, but with conditions | ||
| 10% advance payment or an application fee from buyers while entering into a written agreement for sale; model agreement mandates buyers to pay up to 30% of total consideration on execution of agreement, and additionally, up to 15% of total consideration on completion of plinth work. Remaining payment to be as per clauses mentioned in the model sale agreement. | ||
| *Norms for escrow withdrawal: In line | ||
| 70% of the amount realised by developers to be deposited in a separate account; withdrawal in proportion to the percentage of project completed. | ||
| *Clause for structural defects: In line | ||
| Time frame - Within five years from possession; developers to rectify such defects without further charge | ||
| Odisha | 25-Feb-17 | * Definition of on-going projects: In line |
| Includes projects that are ongoing on the date of commencement of the Act and for which the completion certificate has not been issued | ||
| *Penalties for non-compliance: Diluted | ||
| Compounding of offence clause included to avoid imprisonment; 10% of project cost as penalty. | ||
| *Payment schedule: No clarity in the notified rules | ||
| *Norms for escrow withdrawal: In line | ||
| 70% of the amount realised by developers to be deposited in a separate account; withdrawal in proportion to the percentage of project completed. | ||
| *Clause for structural defects: In line | ||
| Time frame: Within five years from possession; developers to rectify such defects without further charge within thirty days | ||
| Rajasthan | 1-May-17 | * Definition of on-going projects: In line |
| Includes projects that are ongoing on the date of commencement of the Act, and for which the completion certificate has not been issued | ||
| *Penalties for non-compliance: Diluted | ||
| Compounding of offence clause included to avoid imprisonment; 10% of project cost as penalty. | ||
| *Payment schedule: In line | ||
| 10% advance payment, or an application fee from buyers while entering into a written agreement for sale. | ||
| *Norms for escrow withdrawal: In line | ||
| 70% of the amount realised by developers to be deposited in a separate account; withdrawal in proportion to the percentage of project completed. | ||
| *Clause for structural defects: No clarity on number of years | ||
| Time frame: No clarity on number of years from possession; developers to rectify such defects without further charge | ||
| Uttar Pradesh | 27-Oct-16 | * Definition of ongoing projects: Diluted |
| Includes ongoing projects with conditions: excludes projects where: | ||
| - services have been handed over to the local authority for maintenance - where common areas and facilities have been handed over to the association or resident’s welfare association for maintenance | ||
| - all development works have been completed and sale/ lease deeds of | ||
| 60% of apartments/plots/houses have been executed; and | ||
| - where all development works have been completed and application has been filed with the competent authority for issue of completion certificate. | ||
| *Penalties for non-compliance: Diluted | ||
| Compounding of offence clause included to avoid imprisonment; 10% of project cost as penalty | ||
| *Payment schedule: No clarity in the notified rules | ||
| *Norms for escrow withdrawal: In line | ||
| 70% of the amount realised by developers to be deposited in a separate account; but no clarity on withdrawal mechanism | ||
| *Clause for structural defects: No clarity in the notified rules | ||
| Andaman and Nicobar Islands | 31-Oct-16 | In line with central Act |
| Chandigarh | 31-Oct-16 | In line with central Act |
| Dadra and Nagar Haveli | 31-Oct-16 | In line with central Act |
| Daman and Diu | 31-Oct-16 | In line with central Act |
| Lakshadweep | 31-Oct-16 | In line with central Act |
| National Capital | 24-Nov-16 | In line with central Act |
| Territory of Delhi |
Already subscribed? Log in
Subscribe to read the full story →
3 Months
₹300/Month
1 Year
₹225/Month
2 Years
₹162/Month
Renews automatically, cancel anytime
Over 30 premium stories daily, handpicked by our editors


News, Games, Cooking, Audio, Wirecutter & The Athletic
Digital replica of our daily newspaper — with options to read, save, and share


Insights on markets, finance, politics, tech, and more delivered to your inbox
In-depth market analysis & insights with access to The Smart Investor


Repository of articles and publications dating back to 1997
Uninterrupted reading experience with no advertisements


Access Business Standard across devices — mobile, tablet, or PC, via web or app
First Published: May 02 2017 | 7:22 PM IST