Of the 16 major irrigation and power projects approved by the Centre, only five are under execution after a decade, and slow physical progress of those led to an overall cost escalation by 2,341 per cent, a report by the Comptroller and Auditor General of India has said.
In February 2008, the Cabinet had approved a select group of irrigation projects with well-defined deliverables. The five projects that are under execution are Gosirkund project, Teetsa, Saryu, Indira Sagar Poolavaram project, Shahpur-Kandi project.
"The fundamental remained unachieved even after almost a decade of existence of the scheme with only five projects being under actual implementation. A total expenditure of Rs 132.99 bn had been incurred on these five projects as of March 2017," the report said.
Despite this, none of the five projects is near completion and the anticipated benefits in terms of creation of irrigation potential and augmentation of water and power generation were yet to accrue, the report observed.
"The shortfall in terms of physical progress in different components of the projects ranged from eight to 99 per cent in the five projects under implementation along with an overall cost escalation of 2,341 per cent that threatened the economic viability of the projects," the report said.
The CAG attributed the "tardy implementation" to management failures and deficiencies in terms of non-adherence to codal provisions relating to survey and investigation that are an essential ingredient for preparation of detailed project reports, ensuring statutory clearance for the project sites and administrative delays in land acquisition.
The other projects which are yet to see the implementation stage include: Lakhwar project, Renuka Dam project, Kishau project, Ujh project, Ken Betwa project, Kulsi Dam project, Noah Dihing project, Bursar project, 2nd Ravi project, Upper Siang project.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
)