Delay in Golden Quadrilateral
Delhi Some National Highway projects under various phases of National Highways Development Projects (NHDP) have been delayed mainly due to land acquisition, utility shifting, non availability of soil/ aggregates, poor performance of contractors, environment/forest/wildlife clearance, ROB & RUB issue with Railways, public agitation for additional facilities, arbitration/contractual disputes with contractors etc.