Sreedharan presents DPR on Vijayawada Metro to Andhra CM

Image
IANS Hyderabad
Last Updated : Apr 26 2015 | 7:32 PM IST

Delhi Metro Rail Corporation's (DMRC) principal advisor E. Sreedharan on Sunday presented the detailed project report (DPR) on Vijayawada Metro to Andhra Pradesh Chief Minister N. Chandrababu Naidu.

Union minister M. Venkaiah Naidu was also present at the occasion.

Sreedharan said that the total estimated cost of the project (till 2019) is Rs.6,823 crore.

The project comprises two corridors -- corridor 1 (Pandit Nehru Bus Terminal-Penamaluru) for 12.76 km and corridor 2 (Pandit Nehru Bus Terminal-Nidamanuru) for 13.27 km.

While corridor 1 will be linked to the upcoming capital city of Amaravathi, corridor 2 will be connected to Gannavaram airport, Sreedharan said.

The total length of this project is 26.03 km where the cost per kilometer comes up to Rs.209 crore, the DPR states.

"Whether it is going to be elevated or underground will only be decided during the capital development stage," Sreedharan said, adding underground project per kilometer would cost Rs.500-600 crore against Rs.209 crore per kilometer if it is elevated.

Giving a break-up of fares for transportation, the DPR said that the cost of the ticker per person is Rs.10 between 0-5 km, Rs.20 for between 5-10 km and Rs.30 if it is above 10 km.

Explaining the land requirements, the DPR mentions that 31.029 hectares of land (both government and private) will be required for the project. For the construction of Metro Rail Depot, 11. 34 hectares of land will be required, the DPR states.

"Government lands along the route may be reserved for property development to fund the project," the report says.

Sreedharan informed the chief minister that the first phase of the project will begin by June.

By January 1st 2019, one section of the Metro Rail project should be commissioned, said Chandrababu Naidu.

The DMRC team predicted that the traffic demand forecast could be 2.91 lakh trips in 2019-2020 and will rise to 9.99 lakh trips in 2051-52.

Meanwhile, Sreedharan said that the DPR for the Visakhapatnam Metro would be presented by June 15.

Naidu was informed that a Rapid Rail Transit System for Vijayawada, Guntur, Tenali and Mangalagiri (VGTM) could be planned as a metro will not be feasible on this route.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Apr 26 2015 | 7:22 PM IST

Next Story