The 135-km-long Eastern Peripheral Expressway envisages signal-free connectivity between Ghaziabad, Faridabad, Gautam Budh Nagar (Greater Noida) and Palwal.
In a status report filed in the apex court, the NHAI has said that construction work in Haryana was proceeding without any disruption and the issue relating to handing over land of 0.5 km stretch in Sonipat district by the state government to the NHAI has been resolved.
The bench was also informed that some cases pertaining to non-distribution of land acquisition compensation were pending before the district court in Ghaziabad.
The court requested to district judge of Ghaziabad to take up these matters on priority basis as soon as the NHAI approaches the court there.
Besides this, the construction work on the 135-km long Western Peripheral Expressway, which connects Kundli to Palwal via Manesar in Haryana, is also going on.
The court, which has been hearing a 1985 plea filed by environmentalist M C Mehta on various issues including vehicular pollution, had asked the Centre in 2005 to build a peripheral expressway around Delhi by July 2016 to decongest and "de-pollute" the national capital.