With a physical progress completed up to 99.67 per cent, the 1,000 MW first unit is expected to be commissioned in July 2013, the NPCIL website said.
The second unit has completed a physical progress of 94.52 per cent and was expected to be commissioned in March 2014, it said.
NPCIL has been postponing the expected date of commissioning every month.
It is building two 1,000 MW VVER nuclear power units with Russian collaboration at Kudankulam in Tirunelveli district of Tamil Nadu.
The project has missed several deadlines since December last year following protests by locals over safety concerns.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app