DMRC said that the work on the Sector 62 Metro project will start from first week of August even 25 per cent physical work has been done on the Kalindi Kunj-Botanical Garden line.
Regarding the Noida City Centre to Sector 62 (NH24) line, DMRC officers said that civil engineering tenders will be opened on July 20 and work is expected to start on it from the first week of August.
Tree-shifting work coming in the alignment of viaduct station and receiving station is progressing apace and DMRC will provide the design and alignment and list the water supply, power supply and other ducts in this regard. The shift will be effected upon getting the DMRC designs.
Also, underground power lines are being shifted along with optical fibre cable and water lines.
DMRC informed that project work was awarded to SP Singhla company.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app