CAG slams Navy for delay in ASW corvettes project

Image
Press Trust of India New Delhi
Last Updated : Jul 21 2017 | 7:42 PM IST
The Comptroller and Auditor General has come down hard on the Indian Navy for causing inordinate delay in construction of four anti-submarine warfare corvettes.
In a report tabled in Parliament, the federal auditor said two of the four warships were delivered to the Navy were not fitted with required weapons and sensor systems due to which they could not perform to full potential as envisaged.
The CAG was severely critical of the Navy's Directorate of Naval Design (DND) for delay in finalising the design of the corvettes, saying approved designs were amended 24 times.
The Garden Reach Shipbuilders and Engineers Limited (GRSE), a defence public sector undertaking (DPSU), was issued letter of intent for the project in 2003 but major modifications in design of the ships continued till 2008.
The first corvette was delivered to the Navy in July 2014 and second one in November 2015. According to the contract for the project, the third corvette should have been delivered in July 2014 and fourth in April 2015.
"Against the 18 weapons and sensors to be installed on ASW Corvettes, audit observed that the two ASW corvettes delivered were not fitted with 'X' weapon and sensor systems. Thus, ASW corvettes could not perform to its full potential as envisaged," the CAG said.
The auditor also observed that Sea Acceptance Test (SAT) on six weapons and sensors in the first corvette and all weapons and sensors on the second one were pending satisfactory completion.
"Thus, the effectiveness of the main feature of anti- submarine warfare was yet to be fully proved."
(SAT) is conducted to test vessel's speed, equipment, manoeuvrability and safety features.
The CAG also expressed dissatisfaction over licence production and supply of Hawk Mk 132 AJT aircraft by Hindustan Aeronautics Limited.
It said not insisting for licence for manufacture of unlimited number of aircraft by the ministry of defence (MoD) while negotiating for "batch I" contract resulted in avoidable payment of licence fee for licenced manufacture of unlimited number of aircraft.
The CAG also said HAL incurred an expenditure of Rs 107.05 crore on account of procurement of six additional engine kits in anticipation of order from MoD which remained infructuous.
The HAL produces the plane under licence from BAE. Under licence from the BAE Systems.
"Though establishment of facilities for major servicing of airframe and engines was envisaged to be completed by March 2016 and March 2018 respectively, considering aircraft directly procured by MoD, HAL was yet to establish the facilities till date," it said.

Disclaimer: No Business Standard Journalist was involved in creation of this content

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Jul 21 2017 | 7:42 PM IST

Next Story