FGD method is used to remove sulfur dioxide from exhaust flue gases of fossil-fuel power plants.
RInfra EPC has received the letter of approval (LoA) from NTPC for FGD works of its 3x500 MW power plant in Jhajjar, the company said in a statement.
EPC division of RInfra had earlier emerged as L1 bidder amidst competition against leading EPC players including BHEL, L&T, and Mitsubishi Hitachi Power system.
The scope of work includes design, engineering, manufacture, transportation to site, erection and civil work, and testing and commissioning of complete FGD system.
It further said that overall schedule for project is 20 months from the date of LoA for the first unit, with three months additional time each for the two subsequent units.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app