Work on Pink, Magenta lines completed by 80-85%: DMRC

The Pink and Magenta lines will cover areas spread across New Delhi with over 60 stations

Work on Pink, Magenta lines completed by 80-85%: DMRC
Press Trust of India New Delhi
Last Updated : Mar 07 2016 | 7:00 PM IST
Work on the upcoming Pink and Magenta Lines of Delhi Metro, that will cover areas spread across the national capital with over 60 stations, has been completed by 80 and 85% respectively, according to latest DMRC data.

The 58.6-km long Pink Line, once made operational, would be the longest corridor of the rapidly expanding metro grid, touching portions of the inner-ring road and connecting areas such as Mayur Vihar to South Extension.

Read more from our special coverage on "DELHI METRO"



"Progress of civil works upto January 2016 is 80.23%. The line, between Mukundpur and Shiv Vihar, is targeted for completion in December 2016," as per DMRC (Delhi Metro Rail Corporation). The line will have 38 stations.

Another major line, christened Magenta, as part of the Phase III project, will measure 34-km and connect Janakpuri West to Botanical Garden, Noida. There, progress of civil works upto January 2016 is 84.63% with the completion target of December 2016, as per work status till January.

The line will directly connect domestic section of the IGI Airport to south Delhi areas and even Noida. With 23 stations, it will also have inter-change facilities to the already operational Blue, Yellow and Violet lines.

Metro has set October as target to launch its much-awaited 'heritage corridor' that will extend between Central Secretariat and Kashmere Gate bringing historic sites such as Red Fort and Jama Masjid into its operational fold.

"Progress of civil works upto January 2016 on the 9-km long line is 92.35% and is targeted for completion in September 2016," a metro spokesperson said. It was to be ready by December 2015.

Work on the upcoming Dwarka-Najafgarh and the Mundka-Bahadurgarh sections has progressed to 55 and 66% respectively. They are also targeted for completion in December this year.

While there will be three stations in the 4.3-km long Dwarka-Najafgarh, an extension of the Blue Line, the Mundka- Bahadurgarh section, an extension of the Green Line, will have seven stations.

The crisscrossing of the new lines with the existing corridors at many places will take the number of inter-change stations to 27, thus shortening the distance between two different parts of the city by upto 15 km at some places.

Metro was extended to Samaypur Badli on the city's north and till the busy office hub of ITO in the heart of the capital last year.

Ridership had touched a record high of 32.05 lakh on August 28, 2015.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Mar 07 2016 | 6:14 PM IST

Next Story