After commitments made by the government during the Paris Climate Summit in December, the environment ministry notified new standards for thermal power stations relating to consumption of water, particulate matter, SO2, NOx and mercury.
"For capital expenditure, we have a rough estimate around Rs 20,000 crore. These costs fall under the ambit of 'change of law' and hence will be allowed by regulators as a passthrough to consumers," said an NTPC director.
NTPC executives said the cost of power production would increase by Rs 50 lakh per Mw. The current cost of power production is Rs 5 crore per Mw. This translates into a 50-60 paise increase in the final customer tariff.
An executive said NTPC was assessing each of its projects and units for retrofitting. "Some of the plants are partially compliant with the revised standards. Other units require retrofitting," he added.
It will take around six months to complete the initial report before the retrofitting can start. "The cost can go up after we have firmed up the technological part. In some cases, there might be changes in the layout," said the executive.
The industry, however, reckons NTPC's estimate is just half of the real final cost. "The ballpark estimate of increase in cost comes out to be Rs 1-1.40 crore per Mw. This is based on calculations made by the Central Electricity Authority. The variable cost will go up and so will the tariff paid by states to purchase power," said A K Khurana, director-general of the Association of Power Producers.
He said the final tariff was likely to go up by 80 paise per unit. "Apart from the impact on tariffs, the shutdown of 50 per cent of the capacity during retrofitting will hurt grid stability," he added.
The new standards were aimed at improving the air quality in and around thermal power plants, said the government's statement in December. The technology employed should also lead to restrictions on water use and mercury emission. The standards have been made more stringent for new plants and are tighter for those that will be set up in the future.
COAL-BASED POWER TO GET COSTLIER
- New emission norms for coal-based power projects to escalate cost of power production
- NTPC estimates capex of Rs 20,000 cr on retrofitting and plant construction according to new norms
- Power production cost likely to escalate by Rs 50 lakh per Mw
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
)