NHPC expects Rs 300-cr expenses on 280 MW Dhauliganga project

Pproject has completely stopped power generation and it will take at least six more months for operations to resume

Press Trust of India New Delhi
Last Updated : Aug 28 2013 | 5:57 PM IST
State-run NHPC expects to incur expenses worth Rs 300 crore related to damages and restoration of its 280 MW Dhauliganga hydro power project that was impacted by the recent Uttarakhand floods.

The project has completely stopped power generation and it will take at least six more months for operations to resume.

"Due to Uttarakhand floods, the 280 MW Dhauliganga power plant has been completely shutdown. It will take at least another six months to re-start operations there.

Also Read

"The cost, due to the damages and restoration expenses, is estimated to be around Rs 300 crore," NHPC Director (Finance) A B L Srivastava told PTI.

In June, the company had said that floods damaged various ancillary structures of the project like roads, residential and non-residential buildings.

Currently, the leading hydel power producer has an installed power generation capacity of 5,702 MW.

In the wake of the unprecedented floods in Uttarakhand, that resulted in massive devastations, hydro power plants drew flak with some quarters raising concerns that such projects are adversely impacting the environment.

Srivastava said even though the perception about hydro projects "has not been good" after the floods, the fact is "just reverse".

"There is a need to educate the local people and others about the benefits of hydro power," he said.

Making a strong case about viability of hydro projects, he said "the presence of hydro projects actually helped in reducing the impact of the recent floods in Uttarakhand".

"Tehri dam helped in reducing the impact," Srivastava said.

He also emphasised that the potential of hydro power sector in the country is not fully utilised.

NHPC is awaiting approvals for about 10 projects having a total capacity of 8,801 MW. This includes five joint venture projects with cumulative capacity of 3,686 MW.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Aug 28 2013 | 5:55 PM IST

Next Story