Toll collection period in contracts to be extended to compensate operators

India Ratings and Research says the lockdowns would hit infrastructure construction and revenue growth of the implementing companies

highway
The clause, said a National Highways Authority of India official, had been invoked for all such projects, as is allowed in the contracts signed with contractors.
Megha Manchanda New Delhi
2 min read Last Updated : Mar 29 2020 | 12:32 AM IST
With toll collection on national highways suspended across the country amid the Covid-19 crisis, the operators will be compensated through extension of their collection period by the same number of days for which the non-tolling is in force.
 
The government has also invoked the “force majeure” clause — the term for an unforeseeable circumstance or incident that prevents someone from fulfilling a contract. It is included in contracts to remove liability for natural and unavoidable catastrophes that interrupt the expected course of events and restrict participants from fulfilling obligations.
 
The clause, said a National Highways Authority of India official, had been invoked for all such projects, as is allowed in the contracts signed with contractors. So is extension of tolling periods after it is suspended. In the wake of the massive demonetisation exercise in late 2016, highway tolling had been suspended for weeks. And, the companies’ toll collection period was extended by that many days.
 
India Ratings and Research says the massive lockdowns to contain the Covid-19 outbreak would hit infrastructure construction and revenue growth of the implementing companies. Add the fact that many of their workers are returning to their homes in interior parts and are likely to return only after the situation normalises, which could be a month from now or even later. Combined with the fact of continued expenditure in the form of overheads and finance charges and there's a clear hit on profitability.
 
“At this point, nothing is moving from Point A to Point B. Things have come to a standstill and it will take at least three to four months for the work to even begin,” says Jayant D Mhaiskar, chairman of MEP Infra.
 
Even if lockdown is lifted, workers would not be available and there will be restrictions at construction sites, he noted.

One subscription. Two world-class reads.

Already subscribed? Log in

Subscribe to read the full story →
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

Topics :Coronavirustoll collectionNHAI

Next Story