Coal order: Blocks axed on development delays
De-allocation began in 2006, picked up pace in 2012 after CAG found policy for allocations through screening committee route was faulty
)
Explore Business Standard
De-allocation began in 2006, picked up pace in 2012 after CAG found policy for allocations through screening committee route was faulty
)
For the cancellations, the coal ministry cited “no substantial progress in development”, “environment and forest clearance not obtained” and “prospecting licence not taken”.
A case in point is JSPL's Amarkonda Murgadangal block was cancelled in December last year. "All milestones were pending including drilling for detailed exploration could not commence even after a lapse of more than 5 years from the date of allocation," the ministry said.
In the case of Adani Power, the ministry de-allocated Lohara West Extn block arguing anvironmental and forest were not obtained on cut-off date. The project was within the proposed buffer zone of Tadoba-Andheri Tiger Reserve in Maharashtra.
Power generator NTPC Ltd was among the large companies impacted by cancellations. Five of the company's blocks, with over 3 billion tonne reserves, were cancelled in 2012 after a review exercise found major delays in development. However, the blocks were allocated to NTPC again.
Many of the companies impacted by whole-sale cancellations had approached the courts appealing against the government decision. The coal ministry had however proceeded to formulate a policy for allocations based on competitive bidding and has so far allocated 17 blocks to government companies under the new regime.
First Published: Aug 26 2014 | 12:42 AM IST