NHAI, Plancom differ on cost of 4-lane highways

Image
Mihir MishraDevika Banerji New Delhi
Last Updated : Jan 21 2013 | 4:14 AM IST

The cost of building four-lane highways has become another bone of contention between the Planning Commission and the National Highways Authority of India (NHAI). The Plan panel is against an NHAI proposal to increase the cost allocation of building each four-lane highway by 33 per cent from Rs 9 crore a kilometre (km) to Rs 12 crore.

The Planning Commission is of the view that even after factoring in the inflation, the cost estimate is exaggerated. “At 6 to 7 per cent inflation, the cost would only increase to Rs 9.6 crore and not Rs 12 crore, as demanded by NHAI,” said a highly-placed government official, on condition of anonymity.

He added that the Commission saw the cost of building four-lane highways growing to Rs 10.5 crore only after a period of four years and considered that Rs 12 crore was very high. NHAI had recently sent fresh estimates to the Commission, saying Rs 12 crore would be spent on building each km of four-lane highways.

NHAI says the revised cost is based on change in prices of construction material and the wholesale price index (WPI). Assuming the cost of construction material goes up 7-9 per cent a year and WPI increases by 5 per cent per annum, NHAI says the cost of building every km of a four-lane highway could go up to Rs 11.35 crore in 2010-11.

Analysts, too, feel building a four-lane highway at Rs 12 crore per km will be quite high. “The cost of building four-lane highways should rise to a maximum of Rs 9.7 crore a km. Increasing it to Rs 12 crore will be too high,” said Parvesh Minocha, managing director (transport business) at Feedback Ventures, an infrastructure consultancy firm.

Though no official cost estimate for neighbouring countries is available, Minocha said building a four-lane road in Malaysia costs Rs 24 crore per km. The higher cost in Malaysia is on account of better specifications and more expensive labour and machinery costs.

During the tenure of the National Democratic Alliance government, which started the National Highways Development Project, the cost of building a four-lane road was around Rs 4 crore per km.

A committee headed by Planning Commission member B K Chaturvedi, in its report to the government last year, had projected the cost of four- and six-lane highways at Rs 9.5 crore and Rs 10 crore per km, respectively.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Aug 10 2010 | 1:04 AM IST

Next Story