Andhra Pradesh Chief Minister Nara Chandrababu Naidu on Monday, while reviewing the progress of the Polavaram project work, asked the officials to make arrangements for a gallery walk of the spillway on September 3.
Conducting the 71st virtual review at the Secretariat, the Chief Minister said an action plan should be prepared to complete the rehabilitation process by December, adding that officials should camp at Delhi to speed up the clearance of project designs.
During the discussion held with the Board of Chief engineers earlier in the day on Goods and Services Tax (GST) and necessary proposals, Naidu said reports would be sent to the Centre on the same.
He revealed that 57.41 per cent of the project work was completed so far, including 44.23 per cent head works, 42.80 per cent main dam package, 77 per cent excavation works, 33.70 per cent concrete works, 61.75 per cent radial gate works and 94.20 jet grouting works.
Later, Naidu, while conducting a meeting on the progress of several other projects, asked the officials to develop a vision for rainwater harvesting, to ensure that every drop of rainwater gets saved by diverting the water to tanks and reservoirs. He also said that 571 reservoirs should be geotagged so that in case of a dry spell, officials are able to provide water security to people in drought-prone areas.
The Chief Minister made it clear that steps should be taken to supply water to two crore acres including one crore acre of horticulture land. He also said that one crore acres should be covered under micro irrigation in six years, and advised officials to take up digging of larger farm ponds to use the water during the dry spell to save the standing crops through rain guns.
Appreciating the efforts of engineering officials in completing the second phase of Vamsadhara to supply water to Heeramandalam, the Chief Minister said awards would be presented to the collector, joint collector, engineers and contractors. He also advised officials to be careful and monitor the river bunds carefully to prevent breaches during the rainy season.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app