The Completion Certificate has been issued by the authority on 16 January 2020 and has declared the project fit for entry w.e.f. 22 November 2018 and consequently the Company is entitled to maximum bonus of Rs. 14.40 crore in lieu of earlier completion (280 days prior to the schedule completion date) of the said Project.