Faulty planning hits DoNer projects in Arunachal : CAG

Image
Press Trust of India Itanagar
Last Updated : Aug 18 2014 | 2:10 PM IST
Faulty planning process, non-release of funds to the executing agencies and inadequate monitoring has cost Arunachal Pradesh to a great extent in undertaking projects under Non Lapsable Central Pool of Resources (NLCPR) and North East Council (NEC) sponsored by the union DoNER ministry.
The ministry of DoNER during 2008-13 had approved 53 roads and bridges projects (NLCPR-51 and NEC-2) for Arunachal Pradesh involving a total cost of Rs 892.28 crore.
Out of 49 projects sanctioned by the ministry to the state (for the period 2008 - 2013), only 11 were completed, the Comptroller and Auditor General (CAG) of India pointed out in its recent report available here today.
The report highlighted various discrepancies on the part of the state government while undertaking NLCPR and NEC projects in the state.
"There were delays ranging from 7 to 13 months in submission of 'priority lists' to the ministry for sanction of projects and the detail project reports (DPRs) were prepared without proper survey and investigation," the report said.
Criticising the government for delay in releasing fund (3 to 48 months) to the executing agencies against various projects, the report said that the state government did not contribute its share of Rs 12.15 crore towards implementation of 25 NLCPR projects.
"Against the total amount of Rs 403.15 crore released by the ministry till 2012-13 under NLCPR projects, utilization certificates for Rs 111.50 crore were pending as of March 2013," the report pointed out and added that in 22 projects, the executing agencies incurred inadmissible expenditure of Rs 10.16 crore against NLCPR fund.
The report also highlighted that an amount of Rs 5.26 crore had been diverted from three NLCPR/NEC projects by the executing agencies to other projects.
Stating that the completion rate of projects under NLCPR/NEC was far from satisfactory, the report further pointed out that out of 49 projects due for completion by March last year, only 11 projects involving an expenditure of Rs 105.44 crore have been completed.
Even completed projects have time overruns ranging from 12 to 24 months, it pointed out adding, no evaluation study was conducted to assess the impact of projects created.
"Adequate transparency and publicity besides dissemination of information relating to NLCPR and NEC projects was not ensured by the state government through local media and display boards," the report alleged.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Aug 18 2014 | 2:10 PM IST

Next Story