NTPC "requested Ministry of Coal to consider waiver of imposition of Bank Guarantee (BG) to the extent of Rs 138.6 crore as recommended by 23rd IMG (Inter-Ministerial Group) held on 24th and 25th October' 2013 since the block is at an advanced stage and the delay in the start of coal production is beyond the control of NTPC", according to an official document.
"...NTPC stated that all the milestones like mining plan, mine closure plan environment clearance and forest clearance, land acquisition and coal controller permission for the coal block have been completed," the official document said.
"The reasons for non-commencement of the coal production despite of all the clearances can be attributed to lack of support of government of Jharkhand," it added.
The decision to impose the BG was taken following the recommendation of the IMG on coal blocks.
The government had formed the IMG in 2012 to review the progress of coal blocks allocated to firms for captive use and recommend action, including de-allocation.
The panel under the chairmanship of Additional Secretary in the Coal Ministry has members from other ministries, including steel and power.