However, the committee, which will submit its report to the state government by Monday, has noted that had the power utilities completed the transmission network upgrade in Greater Mumbai in a time-bound manner, it would have helped power evacuation from other parts of the state and country.
Further, the committee, which has sourced the necessary backup data from the State Load Dispatch Centre (SLDC), has made a strong case for power generation capacity addition to meet the increasing demand in the city and also exploring options such as roof top solar projects and power generation based on solid waste management.
Sources told Business Standard: “Based on the SLDC data, the committee has noted that the technical fault led to tripping of Tata Power’s unit five at the Trombay plant. However, transmission constraints impacted evacuation of power from the grid, which would have provided relief to the consumers. There will not be witch-hunting but it is committee’s attempt to see that Mumbai’s preeminence as the commercial and financial capital is maintained with an uninterrupted and reliable power supply.”
Concerned over the outage, the state government had asked the committee to look into the causes and recommend short and long-term measures to prevent recurrence. Mumbai’s peak load has already moved to 3,350 Mw against the connected generation of 2,500 Mw. Tata Power, Reliance Infrastructure, BrihanMumbai Electric Supply and Transport (BEST) and state-run Maharashtra State Electricity Distribution Company (MahaVitaran) supply power to the city.
Moreover, the committee has suggested distribution companies can reach an agreement with MahaVitaran for power supply from the state grid. “However, for that to happen, upgradation and strengthening of transmission network is key,” the sources said.
Ashok Pendse, consumer representative at the Maharashtra Electricity Regulatory Commission, shared the committee’s observations. “At present, 1,000 -1,200 Mw is the power deficit in Mumbai. Even if Tata Power’s Unit-6 is converted into coal-fed plant, its capacity will be only 250 Mw,” Pendse added.
He however, suggested that the government will have to expeditiously address the issues relating to right of the way and various clearance which will have way for the utilities to strengthen transmission network.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
)