The land is to be acquired in four affected villages- Talabarkote (440.23 acres), Patra bhag (194.61 acres), Manipur (99.46 acres) and Siaria (61.55 acres).
Notification under section 4 (1) of Land Acquisition Act has already been issued for acquisition of private land for the Gajamara project. NTPC has urged the state government to expedite issue of 6 (1) notification. The Gajamara project needs 1,013 acres.
Besides Gajamara, NTPC had also proposed to set up 1,600 Mw coal-based plant at Darlipalli in Sundergarh district. Odisha will get 50 per cent power from the Darlipalli super thermal plant. This power plant needs 1,652 acres. NTPC hopes to commission this power plant by 2018.
Of 1,274.9 acres private land needed for the power project's main plant, the state government has issued possession certificate for 1,205.79 acres. Alienation proposals for 339.49 acres of government land are in different stages of processing.
Notification under section 4 (1) of Land Acquisition Act has been issued for 32.36 acres of privately owned property required for rehabilitation & resettlement colony. Moreover, administrative approval has been issued for acquisition of 55 acres private land for the Merry Go Round (MGR) system. The Darlipalli super thermal power project will draw water from the Hirakud reservoir in the Mahanadi river. NTPC has secured coal linkage for this project in the form of Dulanga coal block with mine capacity of seven million tonnes per annum (mtpa) under command area of Mahanadi Coalfields Ltd (MCL) and Pakri Barwadih block in Bihar's Hazaribagh district with 12.5 million tonne per annum (mtpa).
NTPC has committed to establish a medical college near Sundergarh, an activity linked to its Darlipalli project.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
)