PGCIL cuts power supply to BSES discoms

Press Trust of India New Delhi
Last Updated : Feb 27 2013 | 1:49 AM IST
Delhi's power supply was on Tuesday lower by 400 Mw, as Power Grid Corporation of India curtailed supply to BSES discoms from last midnight due to non-payment of dues. Officials said PGCIL cut supply of power to BSES Rajdhani Power Ltd (BRPL) and BSES Yamuna Power Ltd (BYPL) from a number of power generation stations. They added there was, however, no significant impact because of the cut in supply. The supply was cut by 260 Mw for BRPL and 160 Mw for BYPL. A BRPL official described the PGCIL action as "arbitrary and unjustified."

"This has happened despite BRPL's best efforts to assure PGCIL of its commitment to pay its dues as also its payment track record. Of the total amount of Rs 321 crore due for the year, BRPL has already paid Rs 308 crore to PGCIL," he said.

More From This Section

First Published: Feb 27 2013 | 12:08 AM IST