The inauguration of the Rs 389.31 crore Ganga pump canal scheme scheduled for today has been cancelled after wall of the canal collapsed during a trial run and inundated areas of a township,
Bihar Chief Minister Nitish Kumar was scheduled to inaugurate the canal scheme, aimed at providing irrigation facilities in the state and neighbouring Jharkhand.
The wall of the canal collapsed when water from the Ganga forcefully hit it after the pump was switched on for trial run at Bateshwarsthan in Bhagalpur district.
The water gushed into Kahalgaon and inundated areas in NTPC township as well some civil areas including the residence of the Kahalgaon civil judge and the sub-judge.
"The proposed programme of the Chief Minister at Bhagalpur today has been cancelled due to technical reasons," an official statement said in Patna yesterday.
Advertisements were yesterday put out in newspapers about the inauguration of the project by the CM in the presence of Water Resources and Irrigation Minister Rajiv Ranjan Singh Lallan and local Congress MLA Sadanand Singh.
RJD workers burnt an effigy of Kumar and Lallan in Bhagalpur alleging corruption in construction of the project.
Principal Secretary of Water Resources department Arun Kumar Singh along with the Bhagalpur DM and SP are on the spot to supervise measures for draining out water from NTPC township and some civil areas of Kahalgaon, around 3 km from the project site.
"Sand bags are being put to check flow of water," Arun Singh told reporters.
It is a joint scheme of Bihar and Jharkhand. Under it 18,620 hectares of land in Bhagalpur would get irrigation facility while 4038 hectares of areas in Godda district of Jharkhand would be irrigated, a government brochure on the project said.
The Rs 389.31 crore project has a total irrigation capacity of 27,603 hectares out of which 22,816 is in Bihar and 4,887 hectares in Jharkhand.
The Planning Commission had originally approved the project in 1977 at an estimated cost of Rs 13.88 crore. The first administrative approval to the project was provided in 2008 involving a cost of Rs 389.31 crore, the brochure said.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
)