NGT raps MoEF over emission standards for thermal power plants

A bench headed by Justice Jawad Rahim came down heavily on the Environment Ministry for not filing the document as per its direction within the stipulated time

NGT seeks details of groundwater use by Delhi Metro
Press Trust of India New Delhi
Last Updated : Sep 24 2017 | 3:23 PM IST
The National Green Tribunal has rapped the Ministry of Environment and Forests (MoEF) for not abiding by its directions on the implementation of a notification on air pollution emission standards and water consumption for coal-based thermal power plants.

A bench headed by Justice Jawad Rahim came down heavily on the Environment Ministry for not filing the document as per its direction within the stipulated time.

Irked at the approach of the ministry, the green panel summoned the Director of the MoEF, who had earlier filed a "misleading" affidavit, and directed him to appear before it on October 4, the next date of hearing.

"Direction issued by us has not been compiled. Though the counsel for MoEF submits that report has been filed which we notice, least we could say about that it is misleading and is not in terms of our direction.

"The affidavit as directed has not been filed. We direct presence of deponent in the affidavit, namely, Dr Sunamani Kereketta, Director, MoEF before the tribunal on the next date of hearing," the bench said.

The lawyer appearing for the MoEF had earlier told the NGT that the ministry was contemplating setting up a committee to ascertain whether the thermal power plants have complied with the notification.

However, the tribunal had declined the suggestion saying that, "having issued the notification its enforcement is the primary and statutory duty of the ministry itself through its instrumentality."

The tribunal was hearing a plea filed by environment activist Sunil Dahiya seeking direction to the Environment Ministry and all the State Environmental Impact Assessment Authority (SEIAA) to ensure that all new approvals comply with the standards provided in the December 7, 2015 notification.

According to the plea, the ministry had promulgated the notification to bring about a reduction in air pollution and water consumption by thermal power plants across the country.

Dahiya had also said that as per the notification, coal thermal power plants installed after January 1 this year should adhere to stricter air pollution norms and the ones installed before December 31, 2016 were given time till December 7, 2017 for compliance.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Sep 24 2017 | 3:23 PM IST

Next Story