IPP's thermal power projects in trouble with 60,000-Mw stressed assets

Absence of long-term PPAs, unavailability of domestic gas supplies deemed as reasons

IPP's thermal power projects in trouble with 60,000-Mw stressed assets
Press Trust of India Mumbai
Last Updated : Nov 23 2017 | 10:20 PM IST

Don't want to miss the best from Business Standard?

Nearly 60,000 mw of thermal power projects in the IPP (independent power producers) segment are stressed mainly for want of long-term power purchase pacts and unavailability of domestic gas supplies, says a report.

According to a report by rating agency Icra, the overall stressed thermal power generation assets remain a sizeable 60,000 mw. Of this about 26,000 mw are in trouble due to the absence of long-term PPAs (power purchase agreements), about 12,000 mw are stranded due to non-availability of domestic gas supply and 22,000 mw due to unviable tariff in the PPAs and capital cost overrun.

The report said the weak financials of state-owned discoms constrain their paying capacity, which along with subdued demand from the industrial segment has affected the demand growth.

"As a result, the overall progress in signing of long-term PPAs through competitive bidding by state-owned discoms remains slow," it said.

The agency said that the 26,000-mw capacity, which does not have long-term PPAs, remains exposed to price and volume risks in the short-term trading market.

"About 60 per cent of this capacity is operational and the balance is under implementation," the report said.

Icra further said the Supreme Court judgement of April 11 this year which disallowed tariff relief to Adani Power and Coastal Gujarat Power of the Tatas and other imported coal-based projects due to change in regulations in Indonesia has impacted a total capacity of 9,000 mw.

"Many of the recently commissioned and under- construction projects with competitively bid-based PPAs remain exposed to the risk of under-recovery of fixed charges due to increase in capital costs following execution delays, exchange rate volatility, funding problems and limited nature of the competitively bid-based tariffs," it said.

The report also noted that gas-based generation capacity of about 12,000 mw in the IPP segment is either stranded or under-utilised due to non-availability of domestic gas and reluctance on the part of the state-run discoms to procure power from them, using imported regasified liquefied natural gas citing higher cost.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Nov 23 2017 | 10:20 PM IST

Next Story