The total cost of state-owned NHPC's Subansiri project in Assam is likely to be around Rs 12,000 crore, nearly double than envisaged initially, following delays on account of various hindrances.

The country's largest hydro power producer, NHPC is executing the 2,000-MW Subansiri hydel plant in Assam. The original cost of the project was Rs 6,285 crore.

"Local issues, contractual issues, geological surprises, delay in decision making and poor risk-taking assessment have impacted the progress on the Subansiri project, which is now likely to cost nearly Rs 12,000 crore," a senior company official told PTI.

Also Read

The project has been stalled since December 2011, after the local people raised issues related to its safety and downstream impact.

"Assam also wanted to increase its total share of power from the project," the official said, adding that the state was earlier granted 208 MW of electricity from the hydel station which has now increased to 300 MW.

Besides, the state is expected to get 25 MW or more free power from the plant which is likely to resume construction work next month. The project, earlier expected to be fully commissioned by December 2012, is now likely to be operational by December 2017.

"We are hopeful that the construction work on the project would start again from December, next month," the official said.

According to sources, the Power Ministry had a meeting with the state government earlier this month and achieved some breakthrough on the issues.

Once commissioned, Subansiri (250x8) will be India's biggest hydroelectric project. The project is located near North Lakhimpur on the border of Assam and Arunachal Pradesh.

The estimated annual energy generation from the project is 7,421 million units.

NHPC generates 5,702 MW electricity from 17 hydel stations in the country. As many as seven power stations with total capacity of 4,095 MW are under construction.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Nov 24 2013 | 11:21 AM IST

Next Story