Kanhar project: NGT lets work on continue, stays new construction

Image
IANS New Delhi
Last Updated : May 07 2015 | 11:07 PM IST

In partial relief to the Uttar Pradesh government regarding the controversial Kanhar dam, the National Green Tribunal on Thursday gave a green signal to the construction already underway but stayed any new construction on the site.

A bench headed by NGT chairperson Justice Swatanter Kumar said: "The project proponent shall complete the construction or activity that is underway and would not commence any new activity or construction without specific recommendations of the committee (set up by the NGT)."

The bench dismissed the applicant's argument that the construction of dam be halted until the the state government sought fresh environmental clearance (EC) as opposed to the nearly 35-year-old consent order of the forest department.

"It would neither serve the interest of the environment or ecology nor would it serve public purpose. Huge amounts have been spent on this project," it noted, adding that any stay on the present construction would further enhance its cost that starkly rose to Rs.2,252.29 crore in 2013 from the original estimation of Rs. 27.75 crore.

Following a petition in the case last year, the green panel Dec 24 stayed the construction of the dam in Uttar Pradesh's Maoist-affected Sonebhadra district as impermissible for lack of a valid EC. It was contended that the previous EC and forest clearance to the Kanhar dam project, first envisaged in 1976, was not valid after over 30 years.

The NGT had set up a committee of experts and officials from the environment ministry as well as the Central Pollution Control Board among others to ensure if the conditions imposed in the consent order of April 14, 1980 as well as February 27, 1982 clearance of the forest department have been "strictly complied" with.

It observed that the EC granted to the project in 1980 was a "mere formality" that failed to safeguard the area's environment and ecology, and adding that "there is need to reassess the environmental impact in the light of the development that has taken place in the area around the project, both within the district and in the entire Singrauli region".

Applicants' advocate Parul Gupta, however, described the judgement as "tilted" in favour of the state government. She said although it upheld the applicants' contention that the old clearances of 1980s served "no good" in view of the present environmental conditions, but it did not stay the construction activity.

"Although certain directions for formation of an expert committee have provided a partial relief, yet the decision gets tilted in favor of the state due to the fait accompli created by them," she noted.

Petitioner Debadityo Sinha from Vindhya Bachao Abhiyan said the judgement had potential to provide limited relief.

"Although the judgment allowed the construction which is underway, it has stated that approval of the Expert Committee would be required for any new construction activity. If these directions are implemented in letter and spirit, it would provide relief to a certain extent," he said.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: May 07 2015 | 11:00 PM IST

Next Story