Zojila pass is situated at an altitude of 11,578 feet on Srinagar-Kargil-Leh National Highway which remains closed during winters (December to April) due to heavy snowfall and avalanches cutting off Leh-Ladakh region from Kashmir.
"The Cabinet Committee on Economic Affairs, chaired by Prime Minister Narendra Modi, has given its approval to the construction, operation and maintenance of 2-lane bi- directional Zojila Tunnel with Parallel Escape (Egress) Tunnel excluding approaches on Srinagar-Leh section connecting NH-1A at Km 95 and at Km 118 in Jammu and Kashmir on engineering, procurement and construction (EPC) mode," the Ministry of Road Transport and Highways said in a statement.
"The project has strategic and socio-economic importance and shall be an instrument for the development of the economically backward districts in Jammu and Kashmir," it said.
The construction period of the project is seven years.
"The civil construction cost of the project is Rs 4,899.42 crore. The total capital cost of the project is Rs 6,808.69 crore. It includes the cost towards land acquisition, resettlement and rehabilitation and other pre-construction activities as well as maintenance and operation cost of tunnel for four years," the statement said.
The project will be implemented by the Ministry of Road Transport and Highways (MoRT&H) through the National Highways and Infrastructure Development Corporation Limited (NHIDCL).
The main objective of the project is to provide all whether connectivity to strategically important Leh region in Jammu and Kashmir which at the moment is limited to at best 6 months because of snow on the passes and threat of avalanches.
"This project along with other ongoing projects like 6.5 km long Z-Morh tunnel at Gagangir would ensure safe, fast and cheap connectivity between the two regions of Kashmir and Ladakh," the statement said.
The government said on completion, it will lead to enormous boost in employment as local businesses get linked to National market and the beautiful region is able to receive round the year tourist traffic.
IL&FS Transportation last year in July had said it has emerged as the lowest bidder for Rs 4,899 crore Zojila pass tunnel in Jammu and Kashmir.
"We wish to inform that the company has emerged as the lowest bidder for the aforesaid (Zojila tunnel) project. The company had quoted an amount of Rs 4,899.42 crore to be constructed in a period of 2,555 days (7 years)," IL&FS Transportation said.
On March 1, 2016, the transport ministry had ordered "re-bidding" for the project, which had been awarded to IRB Infrastructure.
The decision was taken at a high-level meeting, chaired by Gadkari, after Congress leader Digvijay Singh alleged that guidelines were violated while awarding the contract.
The ministry, however, had denied the charges.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app