The four-month-long runway re- surfacing work at Kochi Airport is set to start on Wednesday and there would be flights from 10 AM to 6 PM till March 28, 2020.
Since almost all services have already been re- scheduled between 6 PM and 10 AM, the project period would see cancellation of only five services during the major runway re-surfacing period, a statement from the airport said on Monday.
Cochin International Airport Ltd (CIAL) has started the preparatory work for the project well in advance and thereby ensured the minimal cancellation of services with the co-operation of the airlines, the statement said.
The winter schedule which became effective from the last week of October has already adjusted the services to the available operational time, which sees the cancellation of only one service in international sector-Maldives service operated by Spice Jet- and four services in domestic sector.
Domestic sector is going to have only four cancellations, it said.
CIAL - the seventh busiest airport in the country- - handles 240 aircraft movements and 30,000 passengers a day, expects a rush in early morning and early evening hours as the operational time is going to be stipulated from 24 hrs to 16 hrs.
In view of it, CIAL has decided to increase the check-in time to 3 hrs for the domestic passengers and 4 hrs for the international passengers, the statement said.
Arrangements were already made to ensure hassle-free passenger movement with the help of Customs, Immigration, ground-handling agencies.
The CISF, which manages airport security has deployed 100 additional security men raising their total strength to 950 at Kochi airport.
The agency also decided to deploy another 400 security personnel in the weeks to come.
The airport which started functioning in 1999 underwent first runway re-surfacing work in 2009.
The re-surfing is done to ensure the desired level of friction to facilitate precision landing for the aircraft.
An area of five lakh square meter comprising the 3,400-metre-long runway, with a width of 60 M, and the taxiway, taxiway links would be overhauled during the period.
Simultaneously, CIAL is realigning the lighting system - fixing of central line lights every 15 metres, introduction of new lights at touch-down zones and parking bays, the statement said.
CIAL is spending around Rs 150 crore for the project and expect to complete it as per schedule, it added.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app