The Tori-Balumath stretch is part of the 44-km Tori-Shivpuri railway section, which, the Minister of State for Railways said, would be completed by May.
It will facilitate coal transportation from Central Coalfields Limited's open cast mines Amrapali and Magadh in Jharkhand's Latehar and Chatra districts respectively.
There are three stations, five major bridges, seven road over-bridges and 39 minor bridges between Tori and Balumath.
"The section passes through hilly terrain affected by Maoist and extremists activities. During execution of the project, problems were faced. There was firing at work sites and kidnapping of railway staff and officers by Maoist and extremists," Sinha said.
The minister said with the help of the Jharkhand government, elaborate security arrangements were made during the construction of the line.
"Police camps were set up at sites of the project to ensure round-the-clock work. I thank all the railway staffers for their hard work," he said.
The railways said that as per initial estimate, Coal India Limited (CIL) proposed to transport a total of 80 rakes of coal daily from its various blocks.
Two sidings are being developed by CIL to connect Amrapali and Magadh coal mines to the rail network. It is expected that 15 rakes of coal will be generated from each of the coal mines, it said.
"Work on the remaining part is in advance stage and likely to be completed by May 2018," he said.
The Tori-Balumath section has been completed with an expenditure of about Rs 1,063 crore, the railways said. The revised sanctioned cost of this project is Rs 1,589 crore.
The Tori-Shivpur rail line project is funded by Central Coalfields Limited (CCL) -- a coal producing subsidiary of Coal India Limited (CIL).
The commissioning of Tori-Balumath rail line and Balumath-CCL Siding will help to evacuate five to six rakes of coal everyday in first phase which will result in annual offtake of 6-7 million tonne (MT). On completion of the complete stretch, Tori-Shivpur- Kathotia rail line, around 100 MT of coal will be evacuated annually from North Karanpura Coalfield of Jharkhand, the ministry said in a release.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
