After years of planning and work, Ahmedabad railway bridge runs into wall

Rs 65 crore railway overbridge hits a dead-end as delays in road construction and agricultural zoning hinder completion

Indian Railway
Photo: Shutterstock
Rimjhim Singh New Delhi
3 min read Last Updated : Jan 16 2025 | 12:50 PM IST
Despite investing more than Rs 65 crore and spending six years on construction, the railway overbridge (ROB) built by the Railways and the Ahmedabad Urban Development Authority (AUDA) has hit a wall--literally. The bridge connects the northern and southern parts of the expanded Ahmedabad city and passes over the Gora Ghuma rail yard, according to a report by The Indian Express.
 
While the north-end ramp opens onto the Bopal-Ghuma road, the ramp at the south end is almost obstructed by the boundary walls of private properties in the Manipur-Shilaj area.
 
Five letters sent by the Railways to AUDA between September 2023 and December 2024 highlighted the national transporter's concerns over the unfinished road connecting the south-end ramp of the bridge to the Shilaj main road, located 2 km away. The letters stress that this road, critical for completing the infrastructure, had not yet been constructed, the report said.
 
Dead-end and construction delays
 
The south-end ramp of the ROB nearly touches private property boundary walls, leading to a six-metre-wide dirt track that eventually joins the Shilaj main road. However, this road is not a permanent solution, as it is located within an agricultural zone, complicating construction efforts. Devang P Desai, AUDA chairperson, told Express that the conversion of the zone for development purposes would be necessary before any work could proceed, as mentioned by the report.
 
Change of plans
 
Initially proposed as a Railway Under Bridge (RUB), the project was later modified to a ROB and approved by the Railway Board in January 2018. The bridge, which was expected to alleviate traffic congestion at LC-16A and divert traffic from the nearby LC-15B, has encountered delays. AUDA proposed to build a four-lane ROB in 2019, and construction was finalised by the end of 2024, with the project’s cost shared between AUDA, DFCCIL, and the Railways, the report said.
 
Despite the completion of the bridge, construction of the vital 2 km road connecting the bridge to the Shilaj main road has yet to begin. Several reminders from the Railways to AUDA emphasise the urgency of the situation, but as of January 2025, the road is still not under construction.
 
Future plans
 
The report quoted Desai as saying that the agricultural zoning complicates the situation, and land acquisition or a town planning scheme would be necessary to move forward. However, he added that a partial land acquisition plan is under consideration, with an alignment survey in progress. The road is split between AUDA and AMC jurisdiction, and talks are ongoing with AMC for possible cooperation in construction.
 
While the Ahmedabad Division of Western Railways confirmed that the LC-16A crossing would remain open until the bridge is fully functional, AUDA's Desai noted that the developing area around the bridge makes it harder to address the dead-end situation. He stressed that the goal was long-term planning, despite the current complications, as mentioned in the news report.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

Topics :AhmedabadRailways BS Web Reports

First Published: Jan 16 2025 | 12:50 PM IST

Next Story