Aptel notice to Gujarat solar developers on GUVNL's plea

Gujarat utility had moved tribunal for downward revision of tariff

BS Reporter New Delhi
Last Updated : Nov 13 2013 | 9:15 PM IST
The Appellate Tribunal for Electricity (Aptel) has issued notices to 80 Gujarat-based solar project developers in an appeal filed by Gujarat Urja Vikas Nigam (GUVNL), the state government run utility. GUVNL is seeking a cut in tariff of power it will buy from the solar players on the grounds that actual cost incurred by developers of these projects was 40 percent less than initially assumed.

The utility is seeking a proportionate cut in the tariff to Rs  9 per unit from the Rs  12.54 per unit agreed under the power purchase agreements (PPA). GUVNL has signed PPAs with some eighty players including the solar arms of large corporate groups such as Tata, GMR Essar and Welspun.  

The dispute has put Rs  14,000 crore worth solar projects in the state under a cloud.

The tribunal admitted the appeal with a rider on its maintainability. “Since the maintainability of the Appeal as well as the Petition filed before the State Commission is questioned, we deem it fit to admit this Appeal subject to the maintainability,” Aptel said in its order on Monday.

The hearing in the matter is scheduled on December 11.  

In August, Gujarat Electricity Regulatory Commission (GERC), the state-level regulator had dismissed a review petition. One of the grounds was that the petition was made after three years, while the time allowed for such petitions was 60 days from the original order.

In 2009-10, GERC had determined the tariff through a consultative process. “The Commission decides to adopt Rs .16.50 crores per MW (Megawatt) as capital cost for Solar Photovoltaic (PV) Power Project and Rs .13 crores per MW for Solar Thermal Power Project,” it had said.

Based on these rates, GUVNL signed in aggregate 88 power purchase agreements for 971.5 MW aggregate capacity in two phases. Out of the above, 857 mw of solar PV capacity has been established so far, according to GUVNL.

At the originally agreed cost of Rs  16.5 crore per Mw, the cost of these projects work out to Rs  14,140 crore.

But, GUVNL argues that several developers it had checked had incurred between Rs  10 crore to 13 crore per mw. “The weighted average woks out to around Rs  12 Crore per MW.”

At this rate, the total project cost comes to Rs  10,284 crore or Rs  3,856 crore less.

This difference of Rs  3,856 crore Is a windfall for the developers and will result in additional burden for consumers, the utility argued.

“The increased tariff of Rs . 3.54 per unit is a direct burden on the consumers of the State and is an unwanted, unjustified and windfall gain to the project developers,” the petition said.  

Besides challenging the petition on its maintainability and other technical grounds, developers say that a fall in cost of solar equipment and other costs was taken into account even at the time of fixing the tariff and it was one of the factors that had attracted investment in the renewable energy sector.

Changing terms of PPA long after it was finalised, will affect future investments in the sector they argue.
SUNNY DAYS OVER?
  • 88 PPAs signed between GUVNL and private developers
  • 857 mw solar PV capacity built already in Gujarat
  • Project cost pegged at Rs 16.5 crore per mw by state regulator
  • GUVNL says actual costs much lesser around Rs 12 crore per mw
  • Wants proportionate revision in tarif; Aptel hearing on December 11

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Nov 13 2013 | 8:59 PM IST

Next Story