Delay in gas pipeline projects to hit Tata Power

Company says it is still keen on gas-based plant in Odisha

Image
Jayajit Dash Bhubaneswar
Last Updated : Jan 21 2013 | 5:46 PM IST

Delay in commissioning of gas pipelines passing through Odisha seems to have poured cold water over Tata Power's plan to set up a gas-based power plant in the state.

Tata Power had proposed a 2,000 MW coal-fired power project at Naraj near Cuttack. But, mounting protests from green activists owing to the deleterious impact of emissions from the power station on wildlife at the nearby Chandaka-Dampada sanctuary had forced the company to switch to gas-based mode.

The company had thereafter submitted a revised application to the state government for a gas-based plant, presumably banking on supplies from the Surat-Paradip natural gas pipeline proposed by GAIL India Ltd.

The Surat-Paradip pipeline will cover a distance of 400 km in Odisha. In addition to this pipeline, the 1100-km Kakinada-Howrah pipeline, which is under construction, is set to cover 434 km in the state.

"The gas pipelines are not likely to be commissioned before 2017. Against this backdrop, Tata Power may not be keen on gas-based plant. Since the company has already proceeded significantly on land acquisition and ordered equipment, it is not in a position to wait for five years”, said an energy department official.

Tata Power, however, said it is still keen on the gas-based power plant.

Asked if delay in gas availability would hurt the project's prospects, a company official said, “All I can say is that we are going to stick to the revised application that we have submitted to the state government.”

The company's coal-based plant had hit a roadblock owing to its proximity to the Chandaka-Dampada wildlife sanctuary. The plant site was located within a distance of only 1.5 km and wildlife clearance was mandatory for any project to be located within 10-km radius of a national park or wildlife sanctuary.

This had prompted Tata Power to alter the technology for the power project. The change in technology of the proposed power plant (coal-based to gas-fired) was necessitated by delay in obtaining clearances from the State Wildlife Board and National Wildlife Board, company representatives had earlier informed the state officials.

Tata Power's 2,000 MW project was to come up on 1,000 acres of land. The company had claimed earlier that the land acquisition process was completed and it had paid Rs 100 crore to Odisha Industrial Infrastructure Development Corporation (Idco) towards acquisition cost.

The company had inked an MoU (Memorandum of Understanding) with the Orissa government for establishment of a 1,000 MW coal-based plant on September 26, 2006. It had later proposed to scale up capacity of the power plant to 2,000 MW.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Nov 08 2012 | 11:27 AM IST

Next Story