Currently, road developers can knock the door of NHAI any time after the award of the contract, as there is no restriction on time period.
According to a senior NHAI official, the new Model Concession Agreement (MCA) proposes the time limit of a month within which the developer has to inform NHAI about the event and its impact on the company with full details. “This will reduce the number of disputes and claims from NHAI substantially. The provision will also apply to any monetary settlement or reimbursement,” the official added.
National Highways Builders Federation director-general M Murali said putting a time-frame in the contract for seeking claims would not be feasible. “It (a specific time period) won’t be workable. There has to be some accountability on either side.”
He said the Federation had that to settle disputes, NHAI should pay the amount of claims against the developer’s bank guarantee so that interest costs can be saved.
NHAI has proposed about 50 changes in the MCA. Also, a provision for revising total project cost at the time of financial closure has also been proposed along with withdrawing of any waiver of pre-conditions such as land and environmental clearances.
A proposal in this regard has already been sent to the ministry of road transport and highways for approval, which has formed a committee to look into the matter. The MCA was last revised in 2009 on the recommendations of the B K Chaturvedi committee.
NHAI recently resolved 49 pending claims for Rs 10,550 crore from 26 contractors/concessionaries for final packages worth of Rs 958 crore, according to an official statement. The NHAI Board also resolved various disputes involving three contract packages worth Rs 2,348 crore for an amount of Rs 271 crore. A numbers of disputes are still pending with NHAI.
The roads ministry is in the process of revamping MCA to make it more flexible in line with changing market conditions. Currently, the MCA norms do not give any scope for changes or additions. Earlier, in the absence of such provisions, the government had to come up with a policy for rescheduling premium as well as an exit policy for developers.
“The purpose is to make adjustments in the project costs due to delays that happen at various clearances level and steep increase in input costs. Secondly, in case of any dispute, we should be able to take the decisions at our end rather than going to the highest level authority,” said another NHAI official.
Due to the economic slowdown in the past few years, awarding of contracts for national highways has slowed down. Besides, issues related to environment and forest clearances and land acquisition have come in the way of projects.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
)