Cabinet clears Rs 2,254 cr world-class convention centre at Pragati Maidan
ITPO to put in Rs 1,200 cr, rest to be financed by loans; first phase to be completed by 2019
)
Explore Business Standard
ITPO to put in Rs 1,200 cr, rest to be financed by loans; first phase to be completed by 2019
)
| Major milestones | Time Frame for completion |
| Engagement of Architect Consultant by NBCC | Completed |
| Preparation of DPR | February/March, 2017 |
| Statutory approvals | December, 2016 to April, 2017 |
| Appointment of project executor for IECC project | May, 2017 |
| Dismantling of halls and State/Central Ministry Pavilions | December, 2016 to April, 2017 |
| Execution of work | May, 2017 to May, 2019 |
| Proposed Development | Built-up Area (sq. m.) | |
| Phase-I | Exhibition Space | 1,19,445 (currently 65,000) |
| Convention Centre | 31,630 (New) | |
| Basement Parking | 1,66,130 (New) | |
| Administrative Block | 8,860 (New) | |
| Total | 3,26,065 | |
| Future Expansion | Exhibition Space | 82,480 (additional planned in next phase) |
| Basement | 3,775 (Additional planned in next phase) | |
| Total | 86,255 |
Already subscribed? Log in
Subscribe to read the full story →
3 Months
₹300/Month
1 Year
₹225/Month
2 Years
₹162/Month
Renews automatically, cancel anytime
Over 30 premium stories daily, handpicked by our editors


News, Games, Cooking, Audio, Wirecutter & The Athletic
Digital replica of our daily newspaper — with options to read, save, and share


Insights on markets, finance, politics, tech, and more delivered to your inbox
In-depth market analysis & insights with access to The Smart Investor


Repository of articles and publications dating back to 1997
Uninterrupted reading experience with no advertisements


Access Business Standard across devices — mobile, tablet, or PC, via web or app
First Published: Jan 24 2017 | 1:48 PM IST