Half year past, most Rail based industry projects still in limbo

Only two out of the eight projects announced in the budget of 2013-14 have had their foundation stone laid

Anusha Soni New Delhi
Last Updated : Nov 12 2013 | 1:06 PM IST
The rail ministry has failed to initiate work on a majority of the rail-based industry projects announced in its last Budget in February this year. Six of the eight such initiatives, including a crucial Coach manufacturing unit and a modern signaling equipment facility through the PPP route, have seen no development.

The dismal performance is owing to a perennial funding crunch for the national transporter coupled with the lack of a clear policy on private participation. The tardy progress on the projects adds to the growing list of the rail ministry’s unfulfilled promises three months before the end of this financial year.

“The projects have not taken off. Lack of funds is a major issue. Also, cost sharing agreement and lukewarm response on Public private Partnership (PPP) initiatives has become a problem,” a senior rail ministry official told Business Standard.  Other officials also cited lack of continuity in top leadership as a dampener. The Ministry has witnessed six new ministers assuming office in the past four years alone.

Only two out of the eight projects announced in the budget of 2013-14 have had their foundation stone laid. The plan to set up a Coach Manufacturing Unit in Sonepat is facing delays because of lack of clarity on the new land acquisition law. “The project may need close to 400 acre of land. But as the new land acquisition Act has come, states are seeking clarifications. The exact duration of completion of land acquisition cannot be ascertained,” said a senior official from the Haryana State government closely associated with the project.

Asked about the slow progress on most Rail based industry initiatives, rail minister Mallikarjun Kharge had earlier told Business Standard: “I will soon undertake a review of all the projects that were announced in the rail budget this year.” Other projects which are yet to take off include setting up of a new wagon maintenance workshop in Kalahandi district in Odisha and a Midlife Coach Rehabilitation Workshop in Kurnool in Andhra Pradesh.

The delays have led experts to question Indian Railways’ execution mechanism. “Earlier, projects used to be assessed over the feasibility of location, economic needs of that area and the supporting infrastructure needed before they were announced. We have do not follow this procedure anymore,” former Railway Board Chairman J P Batra told Business Standard.

Senior Railway officials conceded politics plays a major role in decisions involving project execution. “Political compulsions have always over taken the economic concerns in Indian Railways.  But in both these projects, Indian Railways does not have to put any money. It is just the land and assured off-take,” a senior Railway official said.

The only two projects that have seen development are a forged wheel factory that would be set up in Raebareli in collaboration with Rashtriya Ispat Nigam Limited (RINL). RINL will invest Rs 1,100 crore in setting up of the factory. Railways will provide land and guaranteed off-take for 26 years.

The second project involves setting up a Mainline Electrical Multiple Units (MEMU) manufacturing facility at Bhilwara, Rajasthan which is the constituency of former Railway Minister C.P Joshi. The project worth Rs 1000 crore is executed in co-operation with Bharat Heavy Electricals Limited (BHEL).

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Nov 12 2013 | 12:58 PM IST

Next Story