Kudankulam project cost up 14%

Construction began in Sept 2001 with estimated cost at Rs 13,600 cr; expenditure on the project at Rs 15,454 cr till Jan 2013

Image
BS Reporter Chennai
Last Updated : Mar 21 2013 | 11:45 PM IST
The delay in commissioning of the Kudankulam Nuclear Power Plant (KNPP) has pushed the project cost up around 14 per cent. When construction began in September 2001, the government had joined hands with Russia for the project, which was then expected to cost Rs 13,600 crore. But according to the government, till January 2013, expenditure on KNPP was Rs 15,454 crore.

Minister of State in the Prime Minister's Office V Narayanasamy said, the expenditure on Kudankulam Project (KKNPP Units 1&2 - 2 x 1000 Mw) till January 2013 had been Rs 15,454 crore and efforts were being made to commission the first unit in May this year. It may be noted that the project was supposed to go on stream in Sept 2007.

KNPP is in the coastal village of Kudankulam in Tirunelveli district, 650 km south of Chennai. An inter-governmental agreement for the project was signed in Nov 1988 by then Prime Minister Rajiv Gandhi and erstwhile Soviet Union's President Mikhail Gorbachev, for construction of two reactors.

However, the project was in a limbo for a decade due to the political and economic upheaval in Russia after the post-1991 breakup of the Soviet Union. There were also objections from the United States on the grounds that the agreement does not meet the 1992 terms of the Nuclear Suppliers Group (NSG).

Then, the construction began only in September 2001 and the cost was estimated to be $3 billion (around Rs 13,600 crore).

In a statement to the Lok Sabha on Thursday, the minister, said in nuclear power plants, a series of activities including integrated system tests, first criticality, subsequent performance tests, synchronisation of the unit with the grid and raising of power in steps take place.

The nuclear power reactors at Kudankulam employ several safety features to ensure protection of people and the environment even under most stressful situation like extreme natural events leading to a loss of power and cooling water supply, the minister said.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Mar 21 2013 | 9:07 PM IST

Next Story