NHAI to focus on executing contracts where all clearances are in place

The move is aimed at judiciously planning the expenditure by the central government, the NHAI and the NHIDCL

chart
Megha Manchanda New Delhi
Last Updated : Nov 10 2018 | 10:37 PM IST
Tightening its fist on project financing, the road ministry, which aims to construct 30 per cent more roads each day this year, will focus on executing contracts where all requisite clearances are in place. Now, its construction wing — the National Highways Authority of India (NHAI) — is focusing on judiciously planning its expenditure for the current financial year.

The length of highways completed by the Ministry of Road Transport and Highways, the NHAI and the National Highways & Infrastructure Development Corporation Limited (NHIDCL) in 2017-18 was 9,829 km, or roughly 27 km per day.

“This year we would construct 15,000 km or 30 per cent more roads per day than what we did last year,” a senior official said.

Union Road Minister Nitin Gadkari had earlier said the daily day road construction target for the current financial year (2018-19) is 45 km. However, the internal target of the ministry is about 35 km per day by the end of this year, an official said, requesting anonymity.

The move is aimed at judiciously planning the expenditure by the central government, the NHAI and the NHIDCL. “Since the NHAI has to borrow money, we only want to invest in the projects that will give returns. We will also focus on completing the pending projects,” an NHAI official said.

The NHAI's borrowings during the current year are Rs 620 billion. In August, the authority tied up loan worth Rs 250 billion with the State Bank of India.

Experts believe that this is a step in the right direction as project implementation is faster once the necessary clearances are in place. “The approach would ensure that the financial costs incurred can derive economic benefits in the shortest time possible,” said Kushal Kumar Singh, partner, Deloitte Touche Tohmatsu India LLP.

Citing an example, Singh said the Jaipur-Kishengarh six-lane project was executed in 24 months because the land acquisition for the contract was in place.

Even as there is nearly a 30 per cent increase in the per day per kilometre of road construction target for the fiscal, in terms of lane kilometers, the target remains 94 km lane per day by the end of this year. A lane-km is defined as a kilometre-long segment of a road that is a single lane in width. For example, a 1-km stretch of a standard two-lane road represents two lane-kilometre).

One subscription. Two world-class reads.

Already subscribed? Log in

Subscribe to read the full story →
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

Next Story