Andhra CM seeks to speed up Polavaram project

Image
ANI Amaravati, (Telangana) [India]
Last Updated : Apr 16 2018 | 9:55 PM IST

Andhra Pradesh Chief Minister N. Chandrababu Naidu on Monday urged his officials to send letters to Union Water resources minister Nitin Gadkari and Finance minister Arun Jaitley so that funds can be disbursed at the earliest in order to speed up the Polavaram project.

The Polavaram Irrigation Project has reached an overall progress of 52.2% till now, which includes the headworks, the right main canal and the left main canal.

"Out of the different elements of the project, the most progress was seen in the construction of the diaphragm wall. Out of a total 1,427m, this week saw the completion of 42m which leaves 251.4m remaining," said Naidu on the 57th review of the Polavaram project.

"71.3% of the excavation for the spillway and spill channel has been completed, i.e., 795.39 lakh cubic metres out of 1,115.59 lakh cubic metres. Overall, 2.29 lakh cubic metres of earthwork was excavated for the spill channel, pilot channel, spillway, left bank and approach channel," he added.

Out of the 45 proposed colonies for 16,687 houses, work has started on 38 of them and is yet to begin on 7 colonies.

Officials said 15 colonies for Rehabilitation and Resettlement of 3,348 displaced families have been constructed in East and West Godavari. This week, 29,000 cubic metres of earthwork was excavated.

31.36% of the concreting for the spillway and the stilling basin is completed, accounting for 5.14 lakh cubic metres out of 16.39 lakh cubic metres.

This week was the first time that concreting for spillway crossed the milestone of 5,000 cubic metres. Overall, 28,000 cubic metres of concrete was laid this week.

Other main components of the dam that have shown consistent progress are the fabrication of radial gates (58%), jet grouting for the downstream Coffer dam (78%) and upstream Coffer dam (49.6%).

Among the 53 priority projects, Pulakurthy Lift Irrigation Scheme and the Adavipalli Reservoir, which is a part of the HNSS Phase 2, will be completed by April 30.

The main civil works of the Nellore and Sangam Barrages are expected to be finished by May 31.

Disclaimer: No Business Standard Journalist was involved in creation of this content

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Apr 16 2018 | 9:51 PM IST

Next Story