DCM Shriram provides update on expansion of Chlor-Alkali facility and Power plant

Image
Capital Market
Last Updated : Jun 14 2016 | 4:47 PM IST

At Bharuch

DCM Shriram has commissioned 420 TPD of additional Chlor- Alkali capacity at its Unit Shriram Alkali and Chemicals, Bharuch (Gujarat) as a first phase of its expansion project. The balance Chlor-Alkali capacity and the power expansion project will be commissioned in phases by September / October 2016.

The production at Bharuch will increase by 250 TPD till the commissioning of power expansion project. This increased production will be achieved over the next two weeks.

The total Chlor-Alkali capacity of the project has gone up to 1200 TPD w.e.f. 14 June 2016.

Powered by Capital Market - Live News

More From This Section

First Published: Jun 14 2016 | 2:36 PM IST